This policy requires a site masterplan for proposals that form all or part of a site allocation, or in other circumstances the Plan specifies. The masterplan must show how development contributes to the spatial strategy and does not prejudice other parts of the site or adjoining land. It must be submitted with an outline, hybrid or full application, and the first phase of an outline application should be in full detail. It should include a site assessment, a detailed masterplan and a delivery strategy. Applicants must consult the public and stakeholders in line with the Statement of Community Involvement.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
DM3 Masterplans and comprehensive development
Strategic objectives
K Securing the timely delivery of infrastructure
Strategic Policy
A Proposals for development must be accompanied by a site masterplan where
they form all or part of a site allocation, or in other circumstances specified by
the Local Plan. A site masterplan will be expected to set out how development
will contribute to delivery of the spatial strategy for the Borough. It must also
suitably demonstrate that the proposal will not prejudice the future development
of other parts of the site and adjoining land or otherwise compromise the
delivery of the site allocation and outcomes sought for the wider area.
B Where it is specified, a masterplan must be submitted as a component of either
an outline, hybrid, or full planning application. Where an outline application is
submitted, the first phase of development should be submitted in full detail. The
scope and scale of future masterplans should reflect and be proportionate to
the site or area under consideration and where appropriate comprise of:
i. An assessment of the site and its context to inform the overall development
strategy;
ii. A detailed site-wide masterplan that responds positively to the spatial
strategy for the Borough, site specific development principles and
guidelines, and other relevant planning policies; and
iii. A delivery strategy that identifies how the development will be implemented
and managed over its lifetime. This strategy must address any relevant
matters to be resolved such as land assembly and preparation,
infrastructure requirements, development phasing and likely need for
planning obligations and/ or planning conditions, where these are necessary
and appropriate.
C Proposals must address how the development site relates to neighbouring
properties, the surrounding area and where necessary other relevant land
ownerships, particularly in contributing to the delivery of the spatial strategy for
the Borough. Where appropriate, applications will be required to be supported
by a masterplan covering multiple plots within a site allocation to demonstrate
the acceptability and deliverability of the scheme both in terms of its immediate
and wider context. This is additional to the site masterplan required by (A) and
(B) above.
D Applicants must demonstrate that they have appropriately consulted the public
and relevant stakeholders through the masterplan process in accordance with
the latest version of the Council’s Statement of Community Involvement.
Explanation
20.14 To achieve the Local Plan’s vision and strategic objectives it will be important that all
development proposals positively engage with and seek to deliver the spatial
strategy for the Borough. This is particularly vital for the strategic site allocations that
have the potential to deliver new and improved housing, business space, public
realm, facilities and other infrastructure to support the Borough’s residents and
communities. Hertsmere’s diverse supply of strategic sites, which includes
previously developed urban land in addition to large greenfield sites, have their own
specific complexities in terms of their redevelopment. This may include a situation of
multiple land ownership across the site, fragmentation of existing uses and space,
land remediation and need for new or upgraded infrastructure. The Council
considers that these constraints are more likely resolved, and the optimal use of
sites realised, where development is comprehensive and in line with a site-wide
masterplan.
20.15 To help ensure certainty of outcomes, the Council will seek the submission of
masterplans as a key component of the outline, hybrid, or full planning application
process. Submitted masterplans should be informed by a baseline assessment of
the site and its surrounds, drawing on the latest available evidence. This may
include demographic data, economic and social indicators and/or information on the
historical, natural and built environment. The site-wide masterplan itself should
establish the overall approach to the function and form of development. The level of
detail included in the masterplan should be commensurate with nature and scale of
development proposed, along with site-specific requirements. Depending on
individual circumstances, matters to be addressed may include historical and cultural
context; land uses, quantum and distribution of development; layout and design;
access, circulation and parking; open space and landscaping; and infrastructure
(including transport, community and green infrastructure).
20.16 The submitted masterplan’s delivery strategy is important. It will seek to ensure
certainty on outcomes sought from both the individual scheme, and the site
allocation. One of the key aims of the masterplan process is to ensure that
landowners and/ or developers are liaising with each other and made aware of the
planning objectives for the site and wider area. In most cases, it will be mutually
beneficial for the landowners present across an allocation to work positively together
in delivering the site allocation. The Council encourages the development of such
positive relationships. Coordination between landowners and other stakeholders,
including infrastructure providers, will help to ensure that proposals do not prejudice
each other, or the wider development aspirations for the Borough. Sites that are
designed and brought forward comprehensively through the masterplan process will
help to alleviate issues that may arise through piecemeal development and are more
likely to maximise wider public benefits. Nevertheless, the Council acknowledges
that there may be circumstances under which landowners are legitimately unable to
work together. Where this arises, it will be the responsibility of the lead landowner/
developer (who is bringing forward the site-wide masterplan) to demonstrate that
they have made all reasonable efforts to undertake positive and meaningful
engagement with relevant neighbour land interests. The Council requires that this
process should be evidenced and documented as part of the planning application
submission. Those developers seeking to bring forward proposals on their land that
are contrary to emerging or agreed site-allocation wide masterplans will be required
to demonstrate, through appropriate and proportionate technical evidence, that their
scheme is genuinely deliverable and will not prejudice planned-for delivery across
the remainder of the site. Under such circumstances, proposals must also
demonstrate that they accord with the relevant site allocation policy. This is in
accordance with national planning policy. Proposals that prejudice delivery across
the wider site allocation, including impacts upon the scale of development and timing
of housing delivery will be considered correspondingly.
Explanation
20.17 A comprehensive approach to the development of sites will often be in the public
interest, particularly to secure the successful delivery of the spatial strategy for the
Borough. The Council acknowledges that there may be circumstances when it may
be easier for developers to deliver proposals through the piecemeal development or
incremental building out. However, the constraints posed by site boundaries,
neighbouring developments or land uses, along with infrastructure and utilities
(whether at or below the surface), all have potentially limiting consequences for the