The human version

This site allocation covers land south of Allum Lane, Elstree, Borehamwood, a privately owned 10.46 ha site of open and agricultural land in the Metropolitan Green Belt. It is allocated for at least 150 new homes, including specialist accommodation for older people, with healthcare and community facilities, public open space and green infrastructure. Delivery is expected in the first half of the plan period. Planning application 24/0442/FUL proposes an Integrated Retirement Community of 150 homes. Development must keep a strong landscape separation between Borehamwood and Elstree Village, and the setting of the Grade II listed buildings at Nicoll Farmhouse must inform the design. Archaeology near ARCH-17 must be investigated.

An unofficial plain English summary. The official wording below is what counts at examination; check it before you rely on anything here.

Open PDF at p. 419

What the plan says

The text below is extracted automatically from the official PDF and may contain artefacts; the PDF is authoritative.

HBA16 Land South of Allum Lane, Elstree Site Address Land South of Allum Lane, Elstree Site Characteristics Site Size ha Setting Ownership 10.46 ha Urban Extension Private Current Uses Open/agricultural land, including horticultural or equine uses in parts. How Site was Identified Call for Sites / HELAA 2025 CFS-2025-065 and Regulation 18 site-selection work. Planning Designations and Site Considerations Green Belt release/settlement-edge site. Public right of way across the site; TPOs near site edges; archaeological site ARCH-17; potential effects on the setting of two Grade II listed buildings at Nicoll Farmhouse; limited surface- water flood risk and Flood Zone 2 near the eastern edge. The landscape gap between Borehamwood and Elstree Village is a key strategic consideration. Planning Status 24/0442/FUL for an Integrated Retirement Community of 150 homes, associated facilities and relocation/provision of a doctor’s surgery affects most of the site. The allocation extends beyond the application area. Indicative Development Capacity 150 dwellings and healthcare and community provision Timeframe for delivery Strategic objectives C The regeneration of Borehamwood and Potters Bar E Meet the Borough’s housing needs by delivering homes for everyone F Delivering affordable homes K Securing the timely delivery of infrastructure Non-strategic policy Existing Planning Consents 14.237 Planning application 24/0442/FUL seeks to gain full consent for an Integrated Retirement Community of 150 homes, associated facilities and relocation/provision of a doctor’s surgery affects most of the site. The site allocation relates to a wider area. Site Allocation 14.238 Land South of Allum Lane is allocated to deliver at least 150 new homes, including specialist accommodation for older people, together with healthcare/community facilities, public open space, green infrastructure and associated infrastructure. Delivery is anticipated to take place during the first half of the plan period. 14.239 The allocation is located within the Metropolitan Green Belt. The Borough-wide Green Belt Assessment Stage 2 further considers the site’s contribution to the purposes of the Green Belt. It is noted that the site makes a moderate contribution towards both Purpose A and B and is defined as provisional grey belt. The comprehensive development of the urban extension must secure a defensible Green Belt Boundary along the site’s western and southern extent. Opportunities 14.240 This urban extension is in an accessible location, near to Elstree and Borehamwood train station and Borehamwood high street. It provides an opportunity to deliver specialist housing and a new or relocated GP surgery together with additional housing on the wider allocation during the first half of the plan period. 14.241 Comprehensive planning provides an opportunity to establish a high-quality landscape edge, retain a meaningful gap towards Elstree Village, integrate existing rights of way and trees and improve walking and cycling connections to the station, town centre and surrounding neighbourhoods. Year 1-5 Year 6-10 Year 11-17 Beyond Year 17 Development Requirements 14.242 Development must be planned and delivered comprehensively in accordance with Policy DM3. This requires that a site-wide masterplan be prepared demonstrating how the urban extension will deliver a mix of new homes and other compatible uses in accordance with the site allocation. Early development must not prejudice access, landscape, infrastructure, housing capacity or connections required by later phases. 14.243 The masterplan must use the design-led approach to consider how the capacity of the site can be optimised to deliver high-quality and higher density homes. Development must retain and reinforce a strong landscape separation between Borehamwood and Elstree Village. The extent, scale and landscape treatment of development must establish a durable settlement edge and avoid visual or physical coalescence. 14.244 The significance and setting of the Grade II listed buildings at Nicoll Farmhouse must inform the layout, landscape, building scale, materials and important views. A heritage assessment must address cumulative effects across the whole allocation rather than only individual phases. 14.245 Archaeological significance, including the proximity of ARCH-17, must be appropriately investigated. Evaluation and mitigation must be undertaken at a stage that allows significant archaeology to influence the masterplan and disposition of development. 14.246 Existing TPO trees, important hedgerows and other landscape features must be retained wherever practicable and incorporated into the green-infrastructure framework. Replacement planting must reinforce the long-term settlement edge and ecological connectivity. 14.247 The existing public right of way must be retained and enhanced within a safe, direct and overlooked walking network. Development must provide high-quality walking and cycling connections towards the railway station, town centre and Elstree Village. 14.248 Flood Zone 2 and surface-water flood risk must inform the layout. Vulnerable uses must be directed towards areas of lower risk and SuDS integrated with landscape and public open space. Developers should work in partnership with the Environment Agency and engage with them early at pre-application stage, to mitigate against potential flood risk. 14.249 The healthcare facility proposed as part of the site must be appropriately located, accessible by sustainable modes and delivered in accordance with identified primary-care needs and the phasing of development. 14.250 The Borough wide Stage 2 Green Belt Assessment identifies the site as provisional grey belt. Development must establish a strong and permanent Green Belt boundary along the western and southern edges of the released land, using retained hedgerows, woodland and other permanent landscape features. The landscape framework must maintain an effective physical and visual distinction between Borehamwood and Elstree Village. Development Guidance 14.251 Where the wider allocation is delivered in separate phases, design parameters, landscape structure, access and infrastructure should be fixed through the site- wide framework so that later phases form a coherent extension rather than a visually and functionally separate scheme. 14.252 The character of development should be predominantly design-led and residential, with building scale stepping down towards the more sensitive Elstree Village and countryside edges. Higher density should be focused on the most accessible parts of the allocation where it can be accommodated without harm to heritage or landscape separation. 14.253 Specialist housing should be integrated into the wider neighbourhood rather than designed as an isolated institutional campus. Streets, paths, open space and community facilities should be shared and legible, while specialist accommodation should retain appropriate privacy, accessibility and care requirements. 14.254 The GP surgery or other healthcare provision should occupy a visible and accessible location close to principal walking, cycling and public-transport routes. Parking and servicing should be arranged so that the facility can operate effectively without dominating the public realm. 14.255 Development should use retained trees, hedgerows and new structural planting to define neighbourhood edges and frame views. These should be identified through the master planning process. Landscape buffers should perform multiple functions, including biodiversity, SuDS, recreation and visual separation. Applicants are expected to work with Hertfordshire Ecology (or any successor body following LGR) and Herts and Middlesex Wildlife Trust to ensure that open space provision and Biodiversity Net Gain measures incorporate the relevant actions in the LNRS. 14.256 Development should prioritise active travel modes over parking and vehicular access in line with the Local Transport Plan and LCWIP proposals. The masterplan will include a forward-facing car parking strategy that introduces maximum standards for the site that will secure a shift towards a car-lite/ car-free future. 14.257 The public right of way and new active-travel routes should connect directly to internal streets and public spaces and should not be confined to narrow rear corridors. Routes should be overlooked and designed for year-round use.
Nature & environmentSite allocationsTransport & travel📍 Borehamwood📍 Elstree📍 Potters Bar
← Back to the plan search

Have your say

Tips for a response that counts

One focused page beats ten rambling ones. Read the full guide to consultations

  1. Submit a formal representation. This is the only response that must be considered at the plan’s independent examination. The emails below are worth sending too, but they do not count as representations. Open the official response portal

    This portal is one form for the whole plan, and it asks which policy or site allocation you are commenting on. Quote the policy reference and page numbers shown here in your answer so your point is logged against the right part.

    Write your comments before you open the portal: a notes app, an email draft or paper all work. Paste each one in and keep a copy. Ticking policies as you read builds the draft for you on the My response page.

  2. Email your ward councillors. They voted on this plan and represent you. The draft raises the consultation window and the missing costs.
    Not sure of your ward? Find your councillor →
  3. Email the planning policy team with questions about the consultation. Email the policy team

Deadline: 11:59pm, Thursday 19 November 2026. Emails open in your own mail app with a suggested draft. Edit it so it says what you think.