The human version (we wrote this, not the council)
This site allocation covers land south of Allum Lane, Elstree, Borehamwood, a privately owned 10.46 ha site of open and agricultural land in the Metropolitan Green Belt. It is allocated for at least 150 new homes, including specialist accommodation for older people, with healthcare and community facilities, public open space and green infrastructure. Delivery is expected in the first half of the plan period. Planning application 24/0442/FUL proposes an Integrated Retirement Community of 150 homes. Development must keep a strong landscape separation between Borehamwood and Elstree Village, and the setting of the Grade II listed buildings at Nicoll Farmhouse must inform the design. Archaeology near ARCH-17 must be investigated.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
HBA16 Land South of Allum Lane, Elstree
Site Address Land South of Allum Lane, Elstree
Site
Characteristics
Site Size ha Setting Ownership
10.46 ha Urban Extension Private
Current Uses Open/agricultural land, including horticultural or equine uses in parts.
How Site was
Identified
Call for Sites / HELAA 2025 CFS-2025-065 and Regulation 18 site-selection
work.
Planning
Designations and
Site
Considerations
Green Belt release/settlement-edge site. Public right of way across the site;
TPOs near site edges; archaeological site ARCH-17; potential effects on the
setting of two Grade II listed buildings at Nicoll Farmhouse; limited surface-
water flood risk and Flood Zone 2 near the eastern edge. The landscape gap
between Borehamwood and Elstree Village is a key strategic consideration.
Planning Status 24/0442/FUL for an Integrated Retirement Community of 150 homes,
associated facilities and relocation/provision of a doctor’s surgery affects
most of the site. The allocation extends beyond the application area.
Indicative
Development
Capacity
150 dwellings and healthcare and community provision
Timeframe for delivery
Strategic objectives
C The regeneration of Borehamwood and Potters Bar
E Meet the Borough’s housing needs by delivering homes for everyone
F Delivering affordable homes
K Securing the timely delivery of infrastructure
Non-strategic policy
Existing Planning Consents
14.237 Planning application 24/0442/FUL seeks to gain full consent for an Integrated
Retirement Community of 150 homes, associated facilities and relocation/provision
of a doctor’s surgery affects most of the site. The site allocation relates to a wider
area.
Site Allocation
14.238 Land South of Allum Lane is allocated to deliver at least 150 new homes, including
specialist accommodation for older people, together with healthcare/community
facilities, public open space, green infrastructure and associated infrastructure.
Delivery is anticipated to take place during the first half of the plan period.
14.239 The allocation is located within the Metropolitan Green Belt. The Borough-wide
Green Belt Assessment Stage 2 further considers the site’s contribution to the
purposes of the Green Belt. It is noted that the site makes a moderate contribution
towards both Purpose A and B and is defined as provisional grey belt. The
comprehensive development of the urban extension must secure a defensible
Green Belt Boundary along the site’s western and southern extent.
Opportunities
14.240 This urban extension is in an accessible location, near to Elstree and
Borehamwood train station and Borehamwood high street. It provides an
opportunity to deliver specialist housing and a new or relocated GP surgery
together with additional housing on the wider allocation during the first half of the
plan period.
14.241 Comprehensive planning provides an opportunity to establish a high-quality
landscape edge, retain a meaningful gap towards Elstree Village, integrate existing
rights of way and trees and improve walking and cycling connections to the station,
town centre and surrounding neighbourhoods.
Year 1-5 Year 6-10 Year 11-17 Beyond Year 17
Development Requirements
14.242 Development must be planned and delivered comprehensively in accordance with
Policy DM3. This requires that a site-wide masterplan be prepared demonstrating
how the urban extension will deliver a mix of new homes and other compatible
uses in accordance with the site allocation. Early development must not prejudice
access, landscape, infrastructure, housing capacity or connections required by
later phases.
14.243 The masterplan must use the design-led approach to consider how the capacity of
the site can be optimised to deliver high-quality and higher density homes.
Development must retain and reinforce a strong landscape separation between
Borehamwood and Elstree Village. The extent, scale and landscape treatment of
development must establish a durable settlement edge and avoid visual or
physical coalescence.
14.244 The significance and setting of the Grade II listed buildings at Nicoll Farmhouse
must inform the layout, landscape, building scale, materials and important views. A
heritage assessment must address cumulative effects across the whole allocation
rather than only individual phases.
14.245 Archaeological significance, including the proximity of ARCH-17, must be
appropriately investigated. Evaluation and mitigation must be undertaken at a
stage that allows significant archaeology to influence the masterplan and
disposition of development.
14.246 Existing TPO trees, important hedgerows and other landscape features must be
retained wherever practicable and incorporated into the green-infrastructure
framework. Replacement planting must reinforce the long-term settlement edge
and ecological connectivity.
14.247 The existing public right of way must be retained and enhanced within a safe,
direct and overlooked walking network. Development must provide high-quality
walking and cycling connections towards the railway station, town centre and
Elstree Village.
14.248 Flood Zone 2 and surface-water flood risk must inform the layout. Vulnerable uses
must be directed towards areas of lower risk and SuDS integrated with landscape
and public open space. Developers should work in partnership with the
Environment Agency and engage with them early at pre-application stage, to
mitigate against potential flood risk.
14.249 The healthcare facility proposed as part of the site must be appropriately located,
accessible by sustainable modes and delivered in accordance with identified
primary-care needs and the phasing of development.
14.250 The Borough wide Stage 2 Green Belt Assessment identifies the site as
provisional grey belt. Development must establish a strong and permanent Green
Belt boundary along the western and southern edges of the released land, using
retained hedgerows, woodland and other permanent landscape features. The
landscape framework must maintain an effective physical and visual distinction
between Borehamwood and Elstree Village.
Development Guidance
14.251 Where the wider allocation is delivered in separate phases, design parameters,
landscape structure, access and infrastructure should be fixed through the site-
wide framework so that later phases form a coherent extension rather than a
visually and functionally separate scheme.
14.252 The character of development should be predominantly design-led and residential,
with building scale stepping down towards the more sensitive Elstree Village and
countryside edges. Higher density should be focused on the most accessible parts
of the allocation where it can be accommodated without harm to heritage or
landscape separation.
14.253 Specialist housing should be integrated into the wider neighbourhood rather than
designed as an isolated institutional campus. Streets, paths, open space and
community facilities should be shared and legible, while specialist accommodation
should retain appropriate privacy, accessibility and care requirements.
14.254 The GP surgery or other healthcare provision should occupy a visible and
accessible location close to principal walking, cycling and public-transport routes.
Parking and servicing should be arranged so that the facility can operate
effectively without dominating the public realm.
14.255 Development should use retained trees, hedgerows and new structural planting to
define neighbourhood edges and frame views. These should be identified through
the master planning process. Landscape buffers should perform multiple
functions, including biodiversity, SuDS, recreation and visual separation.
Applicants are expected to work with Hertfordshire Ecology (or any successor
body following LGR) and Herts and Middlesex Wildlife Trust to ensure that open
space provision and Biodiversity Net Gain measures incorporate the relevant
actions in the LNRS.
14.256 Development should prioritise active travel modes over parking and vehicular
access in line with the Local Transport Plan and LCWIP proposals. The
masterplan will include a forward-facing car parking strategy that introduces
maximum standards for the site that will secure a shift towards a car-lite/ car-free
future.
14.257 The public right of way and new active-travel routes should connect directly to
internal streets and public spaces and should not be confined to narrow rear
corridors. Routes should be overlooked and designed for year-round use.