This site allocation covers The Former Mercure Hotel, land at Bushey Mill Lane, a privately owned 7.43 ha site with a vacant former hotel, woodland and open land. It is allocated as a strategic employment site, with capacity of c.30,000 sqm of B8 or up to 138,000 sqm of data centre use. Uses could include data centre, storage and distribution, and industrial. It will form part of the wider Tylers Way employment area. The site is provisionally grey belt. Development must be a phased data centre campus under a site-wide masterplan, with a durable Green Belt boundary.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
HBUSA11 The Former Mercure Hotel
Site Address Land at Bushey Mill Lane
Site
Characteristics
Site Size ha Setting Ownership
7.43 ha Urban Extension
(Employment)
Private
Current Uses Vacant former hotel including low-quality woodland/open land and former
dwelling/clearing.
How Site was
Identified
Call for Sites (CFS-2025-087)
Planning
Designations and
Site
Considerations
Green Belt; M1/A41; Hilfield Brook; Flood Zones 2/3; surface-water risk;
woodland/biodiversity; road noise and air quality; limited public transport;
major electricity, water and digital infrastructure requirements.
Planning Status 22/1117/OUT, permission for up to 30,000 sqm B8.
25/1781/FUL, live data centre application proposing 137,410 sqm submitted
for determination.
Indicative
Development
Capacity
c.30,000 sqm B8 or up to 138,000 sqm of data centre use
Timeframe for delivery
Strategic Objectives
A Delivering a better future for Hertsmere
B A thriving local economy
D Support a well-educated and skilled population
G Securing a greener Borough
H Responding to the climate emergency
J Healthy and safe communities
K Securing the timely delivery of infrastructure
Non-Strategic Policy
Existing Planning Consents
16.173 Planning permission 22/1117/OUT provides for 30,000 sqm of B8 industrial storage
provision.
16.174 Planning application 25/1781/FUL seeks the comprehensive redevelopment of the
site for a data centre use, providing over 137,410 sqm floorspace. At the point of the
Local Plan’s Publication, the proposal is still to be determined.
Site Allocation
16.175 The former Mercure Hotel and land contained within its boundary to the immediate
east is allocated as a strategic employment site. The site allocation will deliver
strategic industrial employment that could comprise data centre development,
storage and distribution, industrial and other compatible employment uses. The
delivery of the site allocation will also secure necessary energy, digital, water,
transport and other infrastructure required to support its operation.
16.176 Following delivery, the uses provided across the site will contribute and form part of
the wider Tylers Way employment area. Proposals for the site allocation must retain
and align with the primary strategic employment function of the wider employment
area.
16.177 The Borough-wide Green Belt Assessment Stage 2 concludes that the site makes a
limited contribution to the purposes of the Green Belt. Consequently, the
Assessment Stage 2 concludes that the site is defined as being provisionally grey
belt. The delivery of the site allocation as an employment site must establish a
robust and readily recognisable long-term boundary, making use of the A41/North
Western Avenue, Hilfield Brook and Sandy Lane as permanent physical features
where they coincide with the released area. Where the release boundary adjoins
retained Green Belt to the south-east, it must be reinforced through substantial
Year 1-5 Year 6-10 Year 11-17 Beyond Year 17
structural landscaping and existing permanent landscape or development
boundaries.
Opportunities
16.178 The site occupies a strategically accessible location close to the M1 and A41 and
provides an opportunity to meet specialist employment and digital-infrastructure
requirements that require large sites, high-capacity utilities and strategic
connectivity.
16.179 Redevelopment of the vacant former hotel and other previously developed parts of
the site provides an opportunity to replace underused development with modern
strategic employment infrastructure.
16.180 The scale and location of the site provide an opportunity to consolidate the Tylers
Way employment area and secure investment in electricity, digital and other
infrastructure supporting the wider employment function of the area.
16.181 Hilfield Brook, existing woodland and undeveloped parts of the site provide
opportunities to establish a substantial green and blue infrastructure framework
incorporating habitat enhancement, biodiversity net gain, sustainable drainage and
structural landscape planting.
16.182 Development provides opportunities for local employment, skills and training
associated with construction, engineering, digital infrastructure and the ongoing
operation and maintenance of the site.
16.183 The scale and energy profile of data centre development also provide an opportunity
to investigate the beneficial use of waste heat and other measures which improve
energy and resource efficiency.
Development Requirements
16.184 Development must be delivered as a comprehensively planned and phased data
centre campus. Individual phases must accord with the approved site-wide
development parameters and must not prejudice the delivery of access, utilities,
drainage, landscape, ecological mitigation or other infrastructure necessary to
support later phases.
16.185 Development must be planned and delivered comprehensively in accordance with
Policy DM3. This requires that a site-wide masterplan be prepared demonstrating
how development will deliver strategic industrial employment uses that are in
accordance with the site allocation.
16.186 The masterplan must use the design-led approach to consider how the capacity of
the site can be optimised to deliver high-quality and higher density industrial
employment uses. The masterplan will demonstrate how buildings, access,
servicing, parking, utilities, drainage, landscape and green infrastructure will be
coordinated across the site. Where development is phased, individual phases must
not prejudice efficient development of the remainder of the allocation.
16.187 The development must deliver the highway works and sustainable-transport
measures required through the outline permission and subsequent approvals,
including safe pedestrian and cycle routes and improvements to the public-rights-of-
way network.
16.188 Development proposals must demonstrate that sufficient power and digital
infrastructure can be provided for each phase and for the campus. Necessary
improvements to substations, network reinforcement and other power infrastructure
must be incorporated into the design and landscape framework and delivered
without prejudicing later development.
16.189 Development must demonstrate that adequate water supply, wastewater capacity,
firefighting provision and drainage infrastructure can be provided in step with each
phase. Developers must work with relevant infrastructure providers to ensure that
these requirements can be met within the constraints of their network capacities.
16.190 Development must be informed by a site-specific Landscape and Visual Impact
Assessment. The location, height, scale and massing of buildings, external plant,
yards and associated infrastructure must respond to the site’s high sensitivity to
large-scale employment development and minimise effects on surrounding
countryside and sensitive receptors. Hilfield Brook, woodland, flood-risk land and
other important environmental features should structure the green framework and
provide separation between intensive development and sensitive boundaries.
16.191 The masterplan must establish a durable and readily recognisable boundary to
retained Green Belt, making use of the A41/North Western Avenue, Hilfield Brook
and Sandy Lane as permanent physical features where they coincide with the
released area. Where the release boundary adjoins retained Green Belt to the
south-east, it must be reinforced through substantial structural landscaping and
existing permanent landscape or development boundaries.
16.192 Development must protect and enhance the site’s ecological network, including its
identification as an LNRS ACIB, and deliver biodiversity net gain. Existing woodland
and other important habitats must be retained and enhanced wherever practicable.
Biodiversity net gain and the long-term management of retained and created habitat
must be integrated with the landscape, drainage and open-space strategy.
16.193 Development must provide appropriate local employment, skills, training and
apprenticeship opportunities having regard to both the construction and operational
phases of the development.
Development Guidance
16.194 Building elevations and roofs should use materials, colours and finishes which
reduce the visual prominence of large building forms. Intensive built development
should be concentrated on previously developed and less environmentally sensitive
parts of the site. Loading areas, external storage, plant and service yards should be
located and screened so that they do not dominate sensitive boundaries or principal
views.
16.195 Buildings should be designed for long-term adaptability and efficient use of land. In
the case that data centre development is proposed, opportunities for low-carbon
energy, heat recovery and efficient use of energy and water should be considered as
part of the site-wide infrastructure strategy.
16.196 The layout and infrastructure strategy should allow for technological change,
adaptation and replacement of plant over the lifetime of the development without
requiring significant expansion into retained landscape, ecological or flood-
management areas.
16.197 External lighting should be designed as part of the overall landscape and ecological
strategy for the wider site. This should seek to minimise unnecessary light spill
towards surrounding countryside, habitats and nearby sensitive uses. Security
requirements must be integrated sensitively into the landscape and design. Fencing,
gates, lighting and other security infrastructure should avoid an unnecessarily hostile
or visually intrusive edge to the site.
16.198 Development should prioritise active travel modes over parking and vehicular access
in line with the Local Transport Plan and LCWIP proposals. The masterplan will
include a forward-facing car parking strategy that introduces maximum standards for
the site that will secure a shift towards a car-lite/ car-free future.
16.199 Development adjoining the M1 Motorway should consider the use of land-use
disposition, built form, landscaping and good acoustic design to address noise and
other environmental effects. Necessary acoustic measures and mitigations will be
justified and identified by appropriate and proportionate technical evidence
submitted to the decision-taking process. Developers should demonstrate that they
have undertaken engagement with National Highways.