Site allocation HPBA11

Former Potters Bar Golf Course

On pages 503 to 509 of the official PDF.

The human version

This site allocation covers the Former Potters Bar Golf Course on Darkes Lane, 41.2 ha of privately owned open land. It proposes a strategic urban extension delivering at least 550 homes, including at least 40% genuinely affordable homes and some specialist supported and extra care housing. Plans include reserve land for a primary school and re-naturalising the Potters Bar Brook watercourse. The site has provisional grey belt status, and development must secure a defensible Green Belt boundary on its northern and western edges. A site-wide masterplan under Policy DM3 is required.

An unofficial plain English summary. The official wording below is what counts at examination; check it before you rely on anything here.

Open PDF at p. 503

What the plan says

The text below is extracted automatically from the official PDF and may contain artefacts; the PDF is authoritative.

HPBA11 Former Potters Bar Golf Course Site Address Former Potters Bar Golf Course, Darkes Lane, Potters Bar Site Characteristics Site Size ha Setting Ownership 41.2ha Strategic Urban Extension Private Current Uses Open land, previously used as a golf course. The former club house in use as a gym, and the car park is used for occasional markets. How Site was Identified Call for Sites process Planning Designations and Site Considerations The site is subject to a high level of flood risk; a watercourse runs through the site, and the functional floodplain (FZ 3b) intersects with the proposed vehicular access point onto Darkes Lane. The railway line adjoins the western boundary of the site and, Cranbourne Industrial Estate is located close to the site boundary on the other side of the railway line. An area Tree Preservation Order (TPO) applies to all trees on the site. There are several relevant heritage assets, including Listed Buildings and Darkes Lane West Conservation Area to the north-east, and locally listed structures on-site. Planning Status Live planning application (at 21/09/2026): 26/0427/OUTEI. Outline planning application (with all matters reserved except access) for the phased erection of up to 550 residential dwellings including affordable housing and plots of self-build/custom build homes (Class C3); a community hub building and other community facilities (Class E); green and blue infrastructure; a primary vehicular access from Darkes Lane; a pedestrian and cycle access (and also serving as an emergency access) from Darkes Lane; pedestrian accesses via the Hertfordshire Way; service and utility structures including substations and demolition of the existing club house building and two dwellings. Not yet determined. Indicative Development Capacity 550 dwellings Timeframe for delivery Strategic Objectives A Delivering a better future for Hertsmere E Meet the Borough’s housing needs by delivering homes for everyone F Delivering affordable homes G Securing a greener Borough H Responding to the climate emergency I Celebrating our local identity K Securing the timely delivery of infrastructure J Healthy and safe communities Non-strategic policy Site Allocation 15.160 The site allocation proposes a strategic urban extension to Potters Bar that will deliver at least 550 homes during the plan-period. It will comprise a sustainable new neighbourhood delivering a mix of dwelling sizes, tenures and types to include at least 40% of all new dwellings as genuinely affordable homes and a proportion of specialist supported and extra care housing, alongside an appropriate mix and quantity of compatible commercial, community and main town centre uses. 15.161 The development of the site provides an opportunity to deliver improvements for active travel, flood risk mitigation, and green and blue infrastructure including re- naturalising Potters Bar Brook watercourse. It will deliver new walkable neighbourhoods with an integrated network of walking and cycling routes, including improved active travel networks that access Darkes Lane Local Town Centre and the railway station, and have the potential to extend beyond to adjoining settlements and places, in particular Brookmans Park via the existing right of way alongside the railway line. The delivery of the strategic urban extension will also Year 1-5 Year 6-10 Year 11-17 Beyond Year 17 secure other social and community infrastructure improvements, including reserve land for a primary school, and proportionate investment in local public transport; public realm and environmental enhancements. The latter is anticipated to include new public open space and improvements for nature in line with the aims of the LNRS. 15.162 The Borough-wide Green Belt Assessment Stage 2 further considers the site’s contribution to the purposes of the Green Belt. It concludes that the site is classified as having provisional grey belt status. This is because of the presence of heritage assets across the site. The comprehensive development of the strategic urban extension must secure a defensible Green Belt Boundary to the site’s northern edge to retain the visual separation between Potters Bar and Hatfield. In particular, the existing hedgerows that demarcate the northern edge of the site must be reinforced to ensure the boundary is strong and defensible in perpetuity. Opportunities 15.163 The delivery of the strategic urban extension provides an opportunity to create a new successful and sustainable community located to the north of Potters Bar. It will be a walkable place, with a diverse mix of homes, including genuinely affordable homes that are supported by compatible education, health, community, leisure and recreation facilities. The new neighbourhood will respond positively to the challenges of balancing growth and securing a thriving economy with minimising the impacts of the climate emergency and managing and mitigating flood risk on the site. These new uses will be linked by a comprehensive high- quality green and blue infrastructure network centred around the re-naturalisation of the Potters Bar Brook Main River that runs through the site. Development Requirements 15.164 Development must be planned and delivered comprehensively in accordance with Policy DM3. This requires that a site-wide masterplan be prepared demonstrating how the urban extension will deliver a mix of new homes and other compatible uses in accordance with the site allocation. 15.165 The masterplan must use the design-led approach to consider how the capacity of the site can be optimised to deliver high-quality and higher density homes. It is anticipated that higher intensity mixed-use development could be delivered as part of the new community’s local centre and other appropriate locations across the site where higher density homes may be appropriate. The design and layout of the development should reflect and reinforce the hierarchy of streets and open/green spaces, with a differentiation in design, density, scale and massing, including a range of plot sizes and building heights, with reference to the existing character of Potters Bar. 15.166 As a strategic urban extension, development proposals must be prepared in accordance with Policy HQD1(K) and must be supported by a site-wide Design Code prepared in alignment with the National Model Design Code, or successor guidance. The site-specific design code will be coordinated with the masterplan required by Policy DM3. 15.167 The masterplan must consider the site and its surroundings, including the adjoining motorway, surface water flood risk, the relationship to Darkes Lane Local Town Centre, and the significance of nearby heritage assets especially the Grade II Listed Duty Stone and Darkes Lane West Conservation Area. These factors will inform the siting and massing of built form, open space and important views. 15.168 Development must be phased to ensure the timely provision of the infrastructure necessary to support the strategic urban extension. The potential improvements that could be enabled and delivered through the comprehensive redevelopment of the site are set out as part of the Vision for Potters Bar. These will be funded through a combination of developer contributions (inclusive of CIL) and other sources of funding secured in support of Potters Bar’s regeneration. 15.169 Developers will engage with Hertfordshire County Council Highways (or successor highway authority) at an early stage in the master planning process to gain an understanding of the cumulative traffic impacts of growth and how it can be managed. This work should demonstrably set out a sustainable transport approach to the strategic urban extension, in respect of connectivity and mitigation of highway impacts. It is anticipated that mitigation will include necessary off-site works to rationalise the local highway, reduce severance and enhance sustainable connectivity to services and facilities. The development must be fully integrated with the surrounding street network and facilitate access and permeability through into Potters Bar Darkes Lane Local Town Centre and the station, with enhanced walking and cycle connections between public spaces and surrounding neighbourhoods. 15.170 Delivery of the strategic urban extension will secure a natural landscaped boundary that is informed by the development’s master plan and landscape plan. Specifically, development will provide a defensible Green Belt Boundary to the site’s northern and western edges to retain the visual separation between Potters Bar and Hatfield. The railway line constitutes a strong and permanent Green Belt boundary to the west of the site, and the northern edge of the site is formed of existing trees and hedgerows which can be reinforced with additional native planting to ensure the boundary is visually strong and defensible in perpetuity. 15.171 Developers will work collaboratively with the education authority (Hertfordshire County Council) to determine the requirements for school place provision arising from the delivery of the strategic urban extension. This includes any on-site provision that arises from the strategic urban extension. The developers will work with the education authority to ensure that any agreed on-site provision is delivered in a timely manner to ensure that Potters Bar remains a sustainable and walkable town. 15.172 The delivery of the strategic urban extension must take account of the flood risk that affects the site and incorporate Sustainable Drainage (SuDS) and flood risk attenuation measures into the earliest stages of the layout. Developers should work in partnership with the Environment Agency and engage with them early at pre-application stage, to mitigate against potential flood risk, especially around the main access point to the site from Darkes Lane. 15.173 Applicants should work in partnership with Thames Water to manage surface water, divert existing sewers where applicable and ensure infrastructure upgrades are delivered ahead of the site being occupied. Developers must work positively with the Council and Thames Water to identify any appropriate design-focussed avoidance or mitigation measures relating to the neighbouring Blackbirds Farm Sewage Works. 15.174 Applicants are expected to work with Hertfordshire Ecology (or any successor body following LGR) and Herts and Middlesex Wildlife Trust to ensure that open space provision and Biodiversity Net Gain measures incorporate the relevant actions in the LNRS. This will include the retention and integration of existing on- site TPOs. Development Guidelines 15.175 Development adjoining the railway line should consider the use of land-use disposition, built form, landscaping and good acoustic design to address noise and other environmental effects. Necessary acoustic measures and mitigations will be justified and identified by appropriate and proportionate technical evidence submitted to the decision-taking process. Developers should demonstrate that they have undertaken engagement with Network Rail. 15.176 Development must respond positively to heritage assets including the Grade II listed Duty Stone on the administrative boundary to the northwest of the former Golf Course, and listed buildings at 23 The Avenue and Tiverton, Darkes Lane as well as the Darkes Lane West Conservation Area which directly abuts the north- eastern site boundary. Proposals must address impacts on the significance of these heritage assets and their setting, including the impact on views from within the Conservation Area. Focus should be given to enhancing and revealing the setting and significance of the Duty Stone, which is currently visible from the site, but is not readily accessible being hidden on Network Rail land close to the railway line. 15.177 Applicants will undertake early engagement and work collaboratively with Hertfordshire County Council to explore, identify and agree the potential for the delivery of a new specialised residential provision. This may include the on-site delivery of new provision for children; older persons (to potentially include extra care accommodation); and adults with learning, autism and physical disabilities. 15.178 High-quality public spaces should be created within and around the development which are addressed by positive and/or active building frontages. These should incorporate residential amenity space and play provision that addresses local shortfalls and is accessible to all, and appropriate planting for biodiversity benefit and urban greening as set out in Chapter 10 Green and Blue Infrastructure. 15.179 Development should prioritise active travel modes over parking and vehicular access in line with the Local Transport Plan and LCWIP proposals. The masterplan will include a forward-facing car parking strategy that introduces maximum standards for the site that will secure a shift towards a car-lite/car-free future. 15.180 Developers will be required to carry out necessary geophysical survey and archaeological evaluation to reveal the archaeological potential of the site.
Heritage & characterHomes & housingTransport & travel📍 Darkes Lane📍 Potters Bar
← Back to the plan search

Have your say

Tips for a response that counts

One focused page beats ten rambling ones. Read the full guide to consultations

  1. Submit a formal representation. This is the only response that must be considered at the plan’s independent examination. The emails below are worth sending too, but they do not count as representations. Open the official response portal

    This portal is one form for the whole plan, and it asks which policy or site allocation you are commenting on. Quote the policy reference and page numbers shown here in your answer so your point is logged against the right part.

    Write your comments before you open the portal: a notes app, an email draft or paper all work. Paste each one in and keep a copy. Ticking policies as you read builds the draft for you on the My response page.

  2. Email your ward councillors. They voted on this plan and represent you. The draft raises the consultation window and the missing costs.
    Not sure of your ward? Find your councillor →
  3. Email the planning policy team with questions about the consultation. Email the policy team

Deadline: 11:59pm, Thursday 19 November 2026. Emails open in your own mail app with a suggested draft. Edit it so it says what you think.