HPBA11 Former Potters Bar Golf Course
Site Address Former Potters Bar Golf Course, Darkes Lane, Potters Bar
Site
Characteristics
Site Size ha Setting Ownership
41.2ha Strategic Urban Extension Private
Current Uses Open land, previously used as a golf course. The former club house in use
as a gym, and the car park is used for occasional markets.
How Site was
Identified
Call for Sites process
Planning
Designations and
Site
Considerations
The site is subject to a high level of flood risk; a watercourse runs through
the site, and the functional floodplain (FZ 3b) intersects with the proposed
vehicular access point onto Darkes Lane. The railway line adjoins the
western boundary of the site and, Cranbourne Industrial Estate is located
close to the site boundary on the other side of the railway line. An area
Tree Preservation Order (TPO) applies to all trees on the site. There are
several relevant heritage assets, including Listed Buildings and Darkes
Lane West Conservation Area to the north-east, and locally listed structures
on-site.
Planning Status Live planning application (at 21/09/2026):
26/0427/OUTEI. Outline planning application (with all matters reserved
except access) for the phased erection of up to 550 residential dwellings
including affordable housing and plots of self-build/custom build homes
(Class C3); a community hub building and other community facilities (Class
E); green and blue infrastructure; a primary vehicular access from Darkes
Lane; a pedestrian and cycle access (and also serving as an emergency
access) from Darkes Lane; pedestrian accesses via the Hertfordshire Way;
service and utility structures including substations and demolition of the
existing club house building and two dwellings.
Not yet determined.
Indicative
Development
Capacity
550 dwellings
Timeframe for delivery
Strategic Objectives
A Delivering a better future for Hertsmere
E Meet the Borough’s housing needs by delivering homes for everyone
F Delivering affordable homes
G Securing a greener Borough
H Responding to the climate emergency
I Celebrating our local identity
K Securing the timely delivery of infrastructure
J Healthy and safe communities
Non-strategic policy
Site Allocation
15.160 The site allocation proposes a strategic urban extension to Potters Bar that will
deliver at least 550 homes during the plan-period. It will comprise a sustainable
new neighbourhood delivering a mix of dwelling sizes, tenures and types to include
at least 40% of all new dwellings as genuinely affordable homes and a proportion
of specialist supported and extra care housing, alongside an appropriate mix and
quantity of compatible commercial, community and main town centre uses.
15.161 The development of the site provides an opportunity to deliver improvements for
active travel, flood risk mitigation, and green and blue infrastructure including re-
naturalising Potters Bar Brook watercourse. It will deliver new walkable
neighbourhoods with an integrated network of walking and cycling routes, including
improved active travel networks that access Darkes Lane Local Town Centre and
the railway station, and have the potential to extend beyond to adjoining
settlements and places, in particular Brookmans Park via the existing right of way
alongside the railway line. The delivery of the strategic urban extension will also
Year 1-5 Year 6-10 Year 11-17 Beyond Year 17
secure other social and community infrastructure improvements, including reserve
land for a primary school, and proportionate investment in local public transport;
public realm and environmental enhancements. The latter is anticipated to include
new public open space and improvements for nature in line with the aims of the
LNRS.
15.162 The Borough-wide Green Belt Assessment Stage 2 further considers the site’s
contribution to the purposes of the Green Belt. It concludes that the site is
classified as having provisional grey belt status. This is because of the presence
of heritage assets across the site. The comprehensive development of the
strategic urban extension must secure a defensible Green Belt Boundary to the
site’s northern edge to retain the visual separation between Potters Bar and
Hatfield. In particular, the existing hedgerows that demarcate the northern edge of
the site must be reinforced to ensure the boundary is strong and defensible in
perpetuity.
Opportunities
15.163 The delivery of the strategic urban extension provides an opportunity to create a
new successful and sustainable community located to the north of Potters Bar. It
will be a walkable place, with a diverse mix of homes, including genuinely
affordable homes that are supported by compatible education, health, community,
leisure and recreation facilities. The new neighbourhood will respond positively to
the challenges of balancing growth and securing a thriving economy with
minimising the impacts of the climate emergency and managing and mitigating
flood risk on the site. These new uses will be linked by a comprehensive high-
quality green and blue infrastructure network centred around the re-naturalisation
of the Potters Bar Brook Main River that runs through the site.
Development Requirements
15.164 Development must be planned and delivered comprehensively in accordance with
Policy DM3. This requires that a site-wide masterplan be prepared demonstrating
how the urban extension will deliver a mix of new homes and other compatible
uses in accordance with the site allocation.
15.165 The masterplan must use the design-led approach to consider how the capacity of
the site can be optimised to deliver high-quality and higher density homes. It is
anticipated that higher intensity mixed-use development could be delivered as part
of the new community’s local centre and other appropriate locations across the site
where higher density homes may be appropriate. The design and layout of the
development should reflect and reinforce the hierarchy of streets and open/green
spaces, with a differentiation in design, density, scale and massing, including a
range of plot sizes and building heights, with reference to the existing character of
Potters Bar.
15.166 As a strategic urban extension, development proposals must be prepared in
accordance with Policy HQD1(K) and must be supported by a site-wide Design
Code prepared in alignment with the National Model Design Code, or successor
guidance. The site-specific design code will be coordinated with the masterplan
required by Policy DM3.
15.167 The masterplan must consider the site and its surroundings, including the adjoining
motorway, surface water flood risk, the relationship to Darkes Lane Local Town
Centre, and the significance of nearby heritage assets especially the Grade II
Listed Duty Stone and Darkes Lane West Conservation Area. These factors will
inform the siting and massing of built form, open space and important views.
15.168 Development must be phased to ensure the timely provision of the infrastructure
necessary to support the strategic urban extension. The potential improvements
that could be enabled and delivered through the comprehensive redevelopment of
the site are set out as part of the Vision for Potters Bar. These will be funded
through a combination of developer contributions (inclusive of CIL) and other
sources of funding secured in support of Potters Bar’s regeneration.
15.169 Developers will engage with Hertfordshire County Council Highways (or successor
highway authority) at an early stage in the master planning process to gain an
understanding of the cumulative traffic impacts of growth and how it can be
managed. This work should demonstrably set out a sustainable transport
approach to the strategic urban extension, in respect of connectivity and mitigation
of highway impacts. It is anticipated that mitigation will include necessary off-site
works to rationalise the local highway, reduce severance and enhance sustainable
connectivity to services and facilities. The development must be fully integrated
with the surrounding street network and facilitate access and permeability through
into Potters Bar Darkes Lane Local Town Centre and the station, with enhanced
walking and cycle connections between public spaces and surrounding
neighbourhoods.
15.170 Delivery of the strategic urban extension will secure a natural landscaped
boundary that is informed by the development’s master plan and landscape plan.
Specifically, development will provide a defensible Green Belt Boundary to the
site’s northern and western edges to retain the visual separation between Potters
Bar and Hatfield. The railway line constitutes a strong and permanent Green Belt
boundary to the west of the site, and the northern edge of the site is formed of
existing trees and hedgerows which can be reinforced with additional native
planting to ensure the boundary is visually strong and defensible in perpetuity.
15.171 Developers will work collaboratively with the education authority (Hertfordshire
County Council) to determine the requirements for school place provision arising
from the delivery of the strategic urban extension. This includes any on-site
provision that arises from the strategic urban extension. The developers will work
with the education authority to ensure that any agreed on-site provision is
delivered in a timely manner to ensure that Potters Bar remains a sustainable and
walkable town.
15.172 The delivery of the strategic urban extension must take account of the flood risk
that affects the site and incorporate Sustainable Drainage (SuDS) and flood risk
attenuation measures into the earliest stages of the layout. Developers should
work in partnership with the Environment Agency and engage with them early at
pre-application stage, to mitigate against potential flood risk, especially around the
main access point to the site from Darkes Lane.
15.173 Applicants should work in partnership with Thames Water to manage surface
water, divert existing sewers where applicable and ensure infrastructure upgrades
are delivered ahead of the site being occupied. Developers must work positively
with the Council and Thames Water to identify any appropriate design-focussed
avoidance or mitigation measures relating to the neighbouring Blackbirds Farm
Sewage Works.
15.174 Applicants are expected to work with Hertfordshire Ecology (or any successor
body following LGR) and Herts and Middlesex Wildlife Trust to ensure that open
space provision and Biodiversity Net Gain measures incorporate the relevant
actions in the LNRS. This will include the retention and integration of existing on-
site TPOs.
Development Guidelines
15.175 Development adjoining the railway line should consider the use of land-use
disposition, built form, landscaping and good acoustic design to address noise and
other environmental effects. Necessary acoustic measures and mitigations will be
justified and identified by appropriate and proportionate technical evidence
submitted to the decision-taking process. Developers should demonstrate that
they have undertaken engagement with Network Rail.
15.176 Development must respond positively to heritage assets including the Grade II
listed Duty Stone on the administrative boundary to the northwest of the former
Golf Course, and listed buildings at 23 The Avenue and Tiverton, Darkes Lane as
well as the Darkes Lane West Conservation Area which directly abuts the north-
eastern site boundary. Proposals must address impacts on the significance of
these heritage assets and their setting, including the impact on views from within
the Conservation Area. Focus should be given to enhancing and revealing the
setting and significance of the Duty Stone, which is currently visible from the site,
but is not readily accessible being hidden on Network Rail land close to the railway
line.
15.177 Applicants will undertake early engagement and work collaboratively with
Hertfordshire County Council to explore, identify and agree the potential for the
delivery of a new specialised residential provision. This may include the on-site
delivery of new provision for children; older persons (to potentially include extra
care accommodation); and adults with learning, autism and physical disabilities.
15.178 High-quality public spaces should be created within and around the development
which are addressed by positive and/or active building frontages. These should
incorporate residential amenity space and play provision that addresses local
shortfalls and is accessible to all, and appropriate planting for biodiversity benefit
and urban greening as set out in Chapter 10 Green and Blue Infrastructure.
15.179 Development should prioritise active travel modes over parking and vehicular
access in line with the Local Transport Plan and LCWIP proposals. The
masterplan will include a forward-facing car parking strategy that introduces
maximum standards for the site that will secure a shift towards a car-lite/car-free
future.
15.180 Developers will be required to carry out necessary geophysical survey and
archaeological evaluation to reveal the archaeological potential of the site.