8.1 Proposal HAT - Hatton New Community
Proposal HAT
Hatton New Community
Site Size 262.36ha
Timescale From 2032/33 to 2056/7
Summary and Key Development and Land Use Requirements
In the Plan period to 2050 land within this allocation will be developed broadly in
accordance with the indicative Illustrative Concept Plan above to deliver:
• A minimum of 4,558 new homes, 4,000 of which will be delivered within the
plan period to 2050. Up to 5,250 homes may be delivered depending on
further masterplanning.
• Affordable housing provision in accordance with SWLP Policies, the Strategic
Housing Market Assessment and SWLP Annex B or any successor documents.
• Two three forms of entry primary schools. One six-form of entry secondary
school.
• Provision of one district centre and three neighbourhood centres (as indicated
in the broad locations on the illustrative concept plan) to deliver retail, food
and drink establishments, healthcare provision, community facilities, a
library, other local services/amenities, mobility hubs and workspace
opportunities.
• A minimum of 2ha of local employment provision within the district or
neighbourhood centres, the expansion of the Hatton Technology Park and/or
additional employment land provided at Hatton Country World.
• Enhanced and expanded Hatton Country World facilities around a District
Centre.
• A new spine access road through the site including construction of a new
bridge to traverse the railway line and canal, with provision for buses,
segregated cycleways and segregated footways.
• A comprehensive package of strategic and local infrastructure as set out in
this policy and the Infrastructure Delivery Plan, including significant on and
off-site improvements to rail, sustainable and active travel infrastructure and
highways.
• Primary healthcare facilities to meet the needs of the development as it
expands.
• A comprehensive network of integrated green and blue infrastructure with
provision of a minimum of 25ha of public open space in accordance with
Council requirements.
Sports provision in accordance with the latest Playing Pitch Strategy
and Indoor Sports Facilities studies, but as a minimum provision is
expected to include one leisure centre (located in central core area).
Two adult football pitches.
Three youth football pitches.
Three mini soccer pitches.
One rugby union pitch.
One cricket pitch.
• Provision for self and custom build homes in accordance with policy HO.12.
Vision and Key Principles
The strategic allocation of this new settlement will deliver at least 4,558 homes
together with a comprehensive package of infrastructure and facilities to deliver an
exemplar new community with sustainable transport infrastructure at its heart.
Providing an appropriate mix and size of dwellings in accordance with SWLP polices,
specifically Policy DS.4 in respect of affordable housing. The development will
provide a mix of homes, employment, education, retail, leisure, and community
facilities, delivered across three phases between approximately 2032/33 and beyond
the plan period to 2056/7.
The following key principles will underpin the design and development of Hatton New
Settlement. It will:
• Be shaped by a comprehensive masterplan which will set a vision for a
distinctive townscape based around a concept of three distinct but interlinked
character areas. It will establish a sense of place at the outset influenced by
local character and maximising existing natural assets such as the Grand
Union Canal and Conservation Area.
• Maximise the sustainability of the location by significantly enhancing the rail
facilities at Hatton Station and links to Warwick Parkway Station through a
series of improvements to existing infrastructure and provision of new
infrastructure to serve the railway.
• Be designed to provide a high degree of self-containment and self-sufficiency
regarding transport, active travel, education, healthcare, community, and
green infrastructure. Infrastructure and facilities must be provided at the same
pace as residential development to ensure the needs of residents are met at
each stage of development. Be shaped by the 20-minute walkable
neighbourhood concept where most daily needs can be met within a short
active travel trip with car use minimised. A range of new facilities for new
residents will be provided at an early stage of the development to help
establish sustainable and active travel habits.
• Incorporate an Active Travel Strategy that will integrate an active travel network
with a comprehensive network of accessible, usable and attractive green and
blue infrastructure and open spaces which will be at the heart of the Hatton
community.
The preferred delivery model is for a master developer to oversee the comprehensive
and strategically planned delivery of the site.
Phasing and Summary of Key Infrastructure Requirements
The development will be delivered in three phases, with the delivery of new
infrastructure provision and improvements to existing infrastructure coordinated with
development of each phase and delivered in advance of or alongside development,
rather than retrospectively.
The triggers and phasing for the delivery of new infrastructure and improvements to
existing infrastructure will be set out in the Infrastructure Delivery Plan (or any
successor document). Key infrastructure will be provided on-site with off-site
mitigation measures delivered through pooled S106 contributions in coordination
with key stakeholders.
The development is intended to be phased as follows providing key trigger points:
Phase 1 – Northern Hatton and Canal Paddock – 1,550 dwellings (to be delivered from
2032-2040) to deliver:
• One three form of entry primary school and nursery, including the relocation
of Ferncumbe School.
• Neighbourhood centre around the primary school.
• Neighbourhood centre to the north of Hatton station, including community
mobility hub retail provision, food/drink establishments and satellite health
facilities.
• A car park to serve Hatton Station and a new foot and cycle bridge over the
canal to provide access to the station from phase 1.
• On and off-site highways infrastructure improvements and a realigned and
improved Dark Lane.
Phase 2 – Central and Hatton South – 1,885 dwellings (2036-2046) to deliver:
• One three form of entry primary school and nursery.
• One six form of entry secondary school including sixth form provision.
• This should take the form of a combined ‘all through’ school to include a
nursery, primary school, secondary school and sixth form, should this be
required by the relevant education providers at that time.
• Neighbourhood centre around the secondary school.
• Part of the central core District Centre area including community mobility
hubs, retail provision, food/drink and dining facilities, leisure centre and multi-
service healthcare facilities.
• New Dark Lane spine road including a new bridge over the canal and railway.
• Integration with facilities at Hatton Country World.
Phase 3 – Southern & Eastern Hatton – 1,815 dwellings (2043-2056/7) to deliver:
• Remainder of central District Centre core area, retail provision, primary
healthcare provision, food/drink and dining facilities.
• Safeguarded land for a potential new primary school, depending on an up-to-
date assessment of capacity within the local area.
Development proposals will be required to contribute to the West of Warwick
Sustainable Transport Corridor improving connections to Warwick via Warwick
Parkway in accordance with SWLP Policy ID.5.
Urban Design Principles
• A master developer must set an overall placemaking vision and overarching
design principles for the new settlement to ensure consistent and
complementary high-quality development across the site which delivers a
characterful and distinctive sense of place.
A comprehensive Hatton New Settlement Masterplan and Design Codes will
be produced, which is to be approved by the Local Planning Authority, broadly
having regard to the Illustrative Concept Plan (Figure xx). All development will
be designed and built in accordance with this Masterplan. Existing natural
assets such as the Grand Union Canal and Conservation Area will be
maximised and enhanced.
• Proposals will be expected to demonstrate how they have accounted for the
strategic design principles set out in Policy DS.19.
• Development blocks will be expected to deliver minimum densities of 40
dwellings per hectare. Higher densities will be considered appropriate within
neighbourhood centres and key community facilities including at Hatton
Station.
• Active frontages will be provided in the neighbourhood centre and district
centres.
• Development will be expected to be designed in line with the
recommendations set out in the SWLP Landscape Assessment, the SWLP
Heritage Assessment and the Warwickshire Landscape Guidelines. This will
include excluding land from development on the most elevated parts of the
site (as broadly indicated on the illustrative concept plan and to the east of
Hatton Country World); maintaining key views from the site towards Warwick
and St Mary’s Church; and respecting the setting of the Canal Conservation
Area. Proposals will be expected to protect and enhance the woodland
habitats within and adjacent to the site including copses, ancient woodlands
and in-field trees.
• Active travel will be integral to the development embedding the 20-minute
neighbourhood concept, where daily needs can be met by active or
sustainable travel.
• The Masterplan should prioritise sustainable travel modes over private car use
with streets, facilities and connections designed to make walking, cycling, and
public transport the easiest and most attractive modes.
Active Travel Requirements
The Hatton Masterplan will be informed by an Active and Sustainable Travel Strategy
that will be based on reducing dependency on private cars, creating walkable
neighbourhoods connected by safe and attractive walking and cycling routes,
connected to employment and services by excellent public transport links.
The Strategy will provide an active travel network designed around new community
mobility hubs. Active Travel measures will be integrated with a comprehensive
network of new and enhanced green and blue infrastructure and open spaces to
encourage healthy, active lifestyles.
Active travel provision will include, but is not limited to:
• Provision of four new community mobility hubs at accessible locations in each
phase, in each of the three neighbourhood centres and in the district centre.
• Community mobility hubs will bring together multiple sustainable transport
modes, such as buses, demand responsive transport, shared cars, rentable
bikes and e-scooters together with facilities such as EV charging, secure cycle
parking and parcel lockers. The mobility hubs in the north and central phases
will include public spaces with seating, landscaping, community facilities and
local amenities. The mobility hub in the phase 1 neighbourhood centre will
include a bus interchange to serve Hatton Station.
• In phase 1, delivery of a new foot and cycle bridge over the Grand Union Canal
connecting the new neighbourhood centre with Hatton Station to provide
access for residents of phase 1 and surrounding rural areas to the north.
• In phase 2, developer contributions to deliver a new steps free access
footbridge across the railway with lifts connecting the station with a new
station entrance to the south providing access to existing residents and
residents of phases 2 and 3.
• Developer contributions towards the provision of a new Active Travel link east
of Hatton station in phase 2.
• Enhancements to the existing underpass under the railway and canal to
provide a pedestrian and cycle link to the new active travel link east of Hatton
Station.
• Provision of an east–west Active Travel corridor through a canal side park
linking to an enhanced towpath to enable onward travel to the west and east.
• Developer contributions towards the delivery of significant improvements to
the Grand Union Canal towpath to facilitate access between Hatton Station,
Hatton Locks and Warwick Parkway Station, including new connections to the
towpath.
• Conversion of Dark Lane (between canal and Hockley Road) to a walking &
cycling route.
• Developer contributions towards the delivery of cycleways along the B4439
Hockley Road and A4177 Birmingham Road towards Warwick Parkway,
Warwick, and Leamington Spa.
• Provision of pedestrian and cycleway linkages across the site to provide north-
south and east-west connectivity intersecting development parcels to provide
access to key facilities. This includes active travel provision as part of the new
spine road and new pedestrian and cycle links to access the enhanced Hatton
Station.
• Retention and enhancement of public rights of way crossing the site including
W81, W82, W193, W76 (and variants).
Sustainable Travel Requirements
A Sustainable Transport Strategy will be based on reducing dependency on private
cars, creating walkable neighbourhoods with the provision of safe and attractive
walking and cycling routes, connected to employment and services by public
transport. Significant improvements to rail provision and new bus infrastructure will
be delivered.
Rail
The implementation of strategic plans by rail operators will increase capacity at
Hatton Station meaning the station, together with Warwick Parkway, will have the
capacity to accommodate the anticipated passenger growth from Hatton new
settlement. This will require significant upgrades to Hatton Station in terms of access
and facilities and an increased frequency of service which the new development must
contribute to through a combination of:
• On-site measures as set out in this policy and the Infrastructure Delivery Plan.
• Developer contributions secured in s106 agreements (or any superseding legal
agreements).
• The master-developer (or developers) working collaboratively and proactively
with rail providers and relevant stakeholders including the West Midlands Rail
Executive, Chiltern Railways and Network Rail.
The development will deliver:
• The following on-site:
Active travel routes as set out above, including the new pedestrian and
cycle bridge over the canal between the neighbourhood centre in phase
1 and the station; together with an east-west canal side active travel
corridor making active travel the primary way to access the station.
A new car park and bus interchange to serve the station in the phase 1
neighbourhood centre mobility hub to enable station access via the
new bridge.
Enhancements to the existing underpass under the railway and canal to
connect to a new active travel link east of Hatton Station. The existing
route will be upgraded to a designated public right of way.
• Together with developer contributions and partnership working to provide the
following measures off-site:
Securing a bus service to Hatton Station in phase 1and routing buses to
the new neighbourhood centre bus interchange rather than Station
Approach.
Delivery of a new station pedestrian entrance from Ash Close or
Antrobus Close to include a steps-free access footbridge, via either
extension and improvement of the existing bridge or its replacement.
Improvements to the existing road railway bridge on Station Road, for
example signal control if required by highways providers.
Improved access. waiting areas, signage and welfare facilities.
Provision of a new active travel link east of Hatton Station on Network
Rail land, delivered as part of Phase 2 and connecting to the enhanced
underpass.
Enhancements to the canal towpath to connect the on-site east-west
active travel route onwards towards Warwick Parkway and Warwick.
Car park charging and residents permit parking scheme in the vicinity of
the station, if required.
Additional, secure cycle parking at Hatton and Warwick Parkway
stations.
The potential use of Hatton Loop for rail delivery of construction
materials for later phases.
The increased frequency of rail services must occur early in the
development phasing
Bus
The following measures to ensure the new settlement is well served by bus will be
delivered:
• A high frequency bus service from first occupation, connecting Hatton new
settlement with Warwick Parkway, Warwick, and Leamington Spa secured via
Level of Service Agreement.
• A bus interchange in the phase 1 neighbourhood centre mobility hub to provide
a bus service to Hatton Station.
• High quality bus stops with shelters, seating, raised kerbs and real-time
information within easy reach of all homes.
• Bus priority measures within the site and at key junctions with existing
highways (if feasible).
Access and Highways Requirements
The following highways infrastructure will be directly delivered by the development on
or adjacent to the site:
• A new junction onto the B4439 Hockley Road (eastern) connecting to a
realigned Dark Lane which will be the primary vehicular access for the site,
likely to be via a new signalised junction.
• A new junction onto the B4439 Hockley Road (western) which will be the
secondary vehicular access for the site, likely to be via a ghost island.
• A series of improvements to Dark Lane including but not limited to:
• In phase 1:
Realignment of Dark Lane with a new bridge over the canal to provide a
wider, enhanced route within the site to provide access to early phases.
• In phase 2:
Construction of a new Dark Lane, an ‘all traffic’ spine route from
Hockley Road through the site, with integrated pedestrian and cycleway
provision, linking to Station Road (south of the M40) as per the
illustrative Concept Plan
This will require a new bridge over the railway line and Grand Union
Canal which will require proactive early engagement with relevant
stakeholders such as Network Rail and the Canal & Rivers Trust.
The existing Dark Lane railway bridge and road downgraded to a walking
and cycling route between the Grand Union Canal and Hockley Road,
with vehicle access retained only for existing properties.
In addition, significant mitigation measures to the nearby local and strategic highways
network will be required. Measures will be provided through developer contributions
(with the costs apportioned according to impact) with the masterdeveloper (or
developers) working proactively with highways providers and relevant stakeholders.
Improvements will include, but are not limited to:
• Capacity improvements at A46/A425/A4177 Stanks Island.
• Capacity improvements at M40 J15.
• Capacity & safety improvements at A4177 Birmingham Road / B4439 Hockley
Road junction.
• Upgrade of Dark Lane / Henley Road junction.
• Widening of Dark Lane south of the M40 to enable improved two-way
movement.
• Capacity improvements at A4177 Birmingham Road / Old Budbrooke Road
junction.
Triggers and phasing will be set out in the Infrastructure Delivery Plan.
Education Requirements
New educational facilities (nursery, primary, secondary, Special Resource Provision
facilities and Post 16 facilities) to ensure that provision matches the full needs arising
from the development at the same time as the settlement’s population grows.
The development will deliver:
• Two new primary schools and a secondary school as detailed below.
• A new three form of entry primary school and nursery in phase one in the broad
location shown on the illustrative concept plan. This school will incorporate
relocating the existing Ferncumbe CofE School from Hatton Green.
The primary school will be part of the neighbourhood centre in the
northern development parcel and will be sited adjacent to the mobility
hub which will include a new community building(s) to provide activities
associated with the school, for example before and after school clubs.
• A new six form of entry secondary school with sixth form provision in phase 2,
in the approximate location shown on the illustrative concept plan.
This may comprise an ‘all through’ school, with provision for a nursery, a
three form of entry primary school, and a secondary school on a single
site should this align with needs data and the requirements of relevant
education providers at that time.
Provision of a direct bus route(s) to serve the secondary school to
reduce parent drop-offs by private car.
Alternatively, if an ‘all through’ school is not provided in phase 2 a new
three form of entry primary school will be provided in phase 2 in the
district centre, in the broad location shown on the illustrative concept
plan.
• Additionally, land will be safeguarded in phase 3 for the provision for a further
primary school, should an up-to-date assessment of capacity within the local
area at that time demonstrate sufficient need. If an additional school is not
needed at that time the land will instead be provided as public open space.
Triggers and phasing will be set out in the Infrastructure Delivery Plan.
Healthcare Requirements
• Provision of medical and healthcare facilities as and when these are required
by the Primary Care Trust or the Integrated Care Board, based upon the
proportionate needs arising each stage of the development.
• Healthcare facilities will be provided early in phase 1 to ensure impact on
existing facilities in the local area is mitigated.
• Facilities will be located in the local or district centres and will include primary
care provision such as GP surgeries or satellites, pharmacies and dentists.
• Early engagement with providers has indicated preference for a satellite
primary care facility in phase 1 with a larger new health hub facility in the
district centre in phase 2/3. The master developer (or developers) will continue
to engage proactively with providers to ensure healthcare facilities are
delivered in a strategic and co-ordinated way as the development progresses.
Public Open Space and Sports provision requirements
• Delivery of public open space in accordance with the requirements and levels
of provision set out in Public Open Space SPD or successor documents or
evidence. This will include the following provision:
Parks and gardens including three new parks (covering approximately
25ha) to ensure that all residents of the development are within a five-
minute walk of green space.
Provision of an appropriate range of fully equipped play spaces for
children of all ages, in accordance with the following hierarchy of play
provision:
▪ Local Areas of Play (LAPs).
▪ Local Equipped Areas of Play (LEAPs).
▪ Neighbourhood Equipped Areas for Play (NEAPs). Multi-Use
Games Areas (MUGAs).
▪ Facilities will be provided in accessible locations with good
natural surveillance.
Natural areas including urban woodland.
Allotments/orchards/community gardens.
Informal recreation and picnic areas.
Creation of green corridors as part of the active travel network.
• Delivery of sports facilities in line with the recommendations set out in the
latest published Playing Pitch Strategy and Indoor Sport Facilities Strategy.
• As a minimum provision will include:
One leisure centre
Two adult football pitches, including one 3G pitch adjacent to the
leisure centre
Three youth football pitches
Three mini soccer pitches
One rugby union pitch, within a sports club environment or allocated to
a local club
One cricket pitch within a sports club environment or allocated to a
local club
The pitch provision will include associated changing rooms and
ancillary facilities.
Biodiversity and Green & Blue Infrastructure requirements
• The development will deliver a comprehensive network of green and blue
infrastructure spaces and corridors, based on the landscape character of the
site, which will enhance the attractiveness of the development and sustain a
sense of place, promote a sense of community and social interaction among
residents and encourage health and well-being.
• Development will be required to retain, enhance and incorporate existing
natural assets including the Grand Union Canal and valuable habitats such as
ancient woodland, hedgerows, ponds and veteran, ancient or mature trees.
• The development should be designed to align with the recommendations set
out in the latest published Ecological Assessment, Landscape Assessment
and/or other evidence supporting the SWLP .
• New green infrastructure will link to adjacent networks and public rights of way
wherever possible.
• The development will be required to deliver a minimum of 10% biodiversity net
gain, as agreed with the Warwickshire County Council Ecology and Warwick
District Council Green Spaces teams.
• The delivery of green infrastructure will include an appropriate strategy for the
long-term stewardship and management of the provision.
Environmental Health Requirements
• Provision of adequate noise mitigation measures to mitigate impacts of the
railway and M40 motorway.
• Provision of adequate air quality mitigation measures to mitigate impacts from
the railway, M40 motorway and any other potential sources of air pollution.
• The development will need to be designed to protect the amenity of residents
by considering potential impacts of neighbouring land uses (such as
employment land, sports and leisure facilities etc) and impacts such as
potential noise, light and air pollution.
Historic Environment Requirements
• Development will be expected to be designed and delivered in line with the
recommendations set out in the SWLP Landscape Assessment and SWLP
Heritage Assessment. This includes minimising the harm to the setting and
significance of the Canal Conservation Area, as well as listed buildings within
the site, and in relative proximity, to the site.
• Development will be expected to make suitable provision for the consideration
of archaeology with investigations as required and provision of mitigating
measures if required. These investigations may be required prior to planning
applications.
Flood Risk, Drainage and Water Supply
No built development will be permitted in any part of the areas of the site which fall
within Flood Zones 2 and 3.
The development will be the subject of a comprehensive Flood Risk Assessment and
Drainage Strategy which will:
• Address areas at risk of ground and surface water flooding;
• Integrate sustainable surface water management through the site throughout
the lifetime of the development;
• Identify opportunities for floodwater storage through the provision of
sustainable urban drainage systems (’SuDs’), such as swales, detention
basins, and permeable paving, to store and infiltrate runoff, reducing surface
wa