Chapter 15: Infrastructure
15.1. Introduction
15.1.1 To support the level of economic growth and growth in population as a result of
new housing in this Plan, infrastructure will need to be delivered alongside
homes and jobs in a timely manner. As such this Council will work in partnership
with developers, neighbouring authorities, central government and other
stakeholders to deliver this infrastructure.
15.1.2 An initial ‘Phase 1’ Review of the Infrastructure Delivery Plan (IDP) was
undertaken in May 2024. This updated the 2020 IDP and associated
infrastructure schedules that supported the extant growth in the WNJCS and the
Part 2 Local Plans.
15.1.3 To reflect the comments received through the 2024 Regulation 18 consultation, a
Phase 1 Review (updated) IDP was produced and consulted upon alongside this
2026 Regulation 18 WNLP.
15.1.4 A ‘Phase 2’ review of the IDP has now been undertaken reflecting on the
comments received from stakeholders and partners through the consultation on
that version of the Plan. This takes into account additional infrastructure
required to support the combined WNJCS, WNLP and part 2 plans’ growth. The
IDP and this Infrastructure Chapter set out how applications should deliver
and/or contribute to infrastructure schemes either through financial and/or land
contributions.
15.2. National and local policy context
15.2.1. At the heart of the NPPF is the achievement of sustainable development
through three overarching objectives for the planning system. Part of the
economic objective is to identify and coordinate the provision of
infrastructure (Paragraph 8).
15.2.2. For plan-making the NPPF sets out at paragraph 11 that all plans should
align growth and infrastructure with the requirement that plans be shaped
by early, proportionate and effective engagement between plan makers and
infrastructure providers and operators (paragraph 16. c).
15.2.3. The NPPF (paragraph 20) goes on to state that policies should make
sufficient provision for infrastructure for transport, telecommunications,
security, waste management, water supply, wastewater, flood risk and
coastal change management, and the provision of minerals and energy
(including heat); and community facilities (such as health, education and
cultural infrastructure).
Planning Practice Guidance
15.2.4. Planning Practice Guidance (PPG) contains details on planning obligations
and states that they should assist in the mitigation of impact of unacceptable
development to make it acceptable in planning terms. It makes provision for
policies to be set out in plans and examined in public to ensure clarity from
the outset.
15.2.5. The policies relating to planning obligations and infrastructure will be
informed by viability assessments that consider affordable housing and other
policy requirements.
One West Northamptonshire Plan
15.2.6. The One West Northamptonshire Plan sets out five guiding principles and
seven priorities for the authority.
15.2.7. The provision of suitable and timely infrastructure to support the existing and
proposed population of West Northamptonshire will contribute to achieving
these priorities. Specifically, timely delivery of infrastructure will help create
sustainable, thriving and connected environments for West
Northamptonshire’s population ensuring it is a great place to grow up and
age well.
15.2.8. To achieve the above priorities this Plan supports the provision of
infrastructure that will help achieve Net Zero as set out by central
government. The Plan contains policies relating to electric vehicle charging
infrastructure and requires development to be linked sustainably to existing
and planned for facilities and amenities. New developments will be
connected and will need to prioritise foot, cycle, wheeling and public
transport modes before the individual car where possible; developments will
need to demonstrate how people will travel sustainably through a detailed
Travel Plan for the development.
15.2.9. To improve the life chances and reduce inequalities of people living and
working with West Northamptonshire, quality educational infrastructure will
be required to support growth.
15.2.10. West Northamptonshire Council is the Local Education Authority and has a
statutory duty to provide sufficient school places for children within its
boundary. Housing development will generate the need for new places either
through new schools or extensions to existing and will consist of provision for
early years, primary, secondary and SEND school places. The School
Organisation Plan (SOP) for West Northamptonshire sets out the number of
new places needed on a 5-year basis. The current version SOP has informed
the IDP for this Plan.
15.2.11. Green infrastructure and open space will need to be provided alongside
development. As set out in the Built and Natural Environment chapter, this
will either be provided on-site or through improved provision off-site. Where
it is located off-site, sustainable links from development to the infrastructure
will be required to ensure people have access to environments that enable
healthier lifestyles. In some cases, some open space may also contribute to
biodiversity net gain and nature recovery networks. Whilst this is not
infrastructure required to support development; it is a statutory requirement
for developers to ensure that a net gain in biodiversity is achieved to support
the overall ambitions for environmental protection within the UK.
15.2.12. Infrastructure to allow high speed electronic and digital communications will
be a core infrastructure component for new development, allowing people
and businesses to be connected and to continue to build a strong economy.
15.2.13. This Plan and its IDP have been informed by current information from utility
providers who have identified where existing capacity or new infrastructure is
needed to support growth. Connections to electric, gas and any other
emerging energy grids is a requirement of development; developers are
expected to have started conversations with providers early on in the
planning process.
15.2.14. To ensure the residents of West Northamptonshire are able to lead healthy
lives with fewer health inequalities, healthcare infrastructure will need to be
delivered alongside new residential development. This can be achieved
through increasing existing providers’ capacity, such as GPs and surgeries
but can also include other measures such as embedding sustainable
transport choices that enable residents and visitors to make healthy choices
when travelling and spending their leisure time.
15.3. Evidence base summary
15.3.1. This Plan has been informed by an up-to-date HENA. The HENA uses current
census population data and forecasting to reach housing and employment figures
and has been appraised for viability against policy requirements of the Plan.
15.3.2. To support growth, the Council has worked with partners to identify the
infrastructure needed to mitigate the impacts of development building on the
initial ‘Phase 1’ update of the West Northamptonshire Infrastructure Delivery Plan
(IDP) as set out above.
15.3.3. The IDP has been produced to sit alongside this Plan and inform policies within
it. It will be updated regularly to take account of delivered and /or new schemes
and any new information coming forward in terms of funding opportunities and
partnerships.
15.3.4. The IDP infrastructure schedule tables identify schemes within the following
categories:
• Transport
• Healthcare
• Education
• Community and Leisure – including libraries, social care, burial
grounds
• Open Space, Green Infrastructure and Biodiversity Net Gain
• Utilities including water management
• Fire and Police
• Waste management
• Digital and telecoms
15.3.5. The Council has worked extensively with the following partners (not exhaustive)
to help inform the IDP and moving forward, to help deliver West
Northamptonshire’s infrastructure:
• Northamptonshire Police
• Northants Fire and Rescue
• National Highways
• Anglian Water
• Thames Water
• Severn Trent Water
• The Environment Agency
• Natural England
• Historic England
• National Grid
• South East Midlands Local Enterprise Partnership (SEMLEP) in the early stages
of plan preparation
• England’s Economic Heartland
15.3.6. The policies within this section of the Plan set out how the delivery of that
infrastructure will come forward and detailed infrastructure requirements are set
out in the IDP for West Northamptonshire.
15.3.7. Details on and policies relating to open space, community needs and green
infrastructure can be found in relevant sections of this Plan and applicants should
read the Plan as a whole to understand the infrastructure requirements of their
proposals.
15.4. Funding mechanisms
15.4.1. Infrastructure that is required to serve the current and future needs of West
Northamptonshire is expected to be delivered through a variety of mechanisms
including Sections 106 (Town and Country Planning Act 1990) 111(Local
Government Act 1972) and 278 (Highways Act 1980), Community Infrastructure
Levy (CIL), and Strategic Access Management and Monitoring (SAMM) fees. In
some cases, infrastructure may be able to be funded through Government and
partnership funding pots.
15.4.2. West Northamptonshire has three CIL charging schedules for the former
Daventry, Northampton and South Northamptonshire areas. The CIL is a
viability tested charge on most forms of new development. Unlike S106
obligations CIL monies can be used to help fund a wide range of infrastructure
projects including strategic infrastructure not necessarily directly related to the
development the CIL monies are accrued from.
15.4.3. The SAMM payments have historically been required for new housing within
3km of the Upper Nene Valley Gravel Pits Special Protection Area (SPA). The
most recent evidence commissioned by the Council extends this zone of
influence to 5.9km a position taken forward in this plan. Details on developer
requirements can be found in the West Northamptonshire Upper Nene Valley
Gravel Pits Special Protection Area Guidance and Mitigation Strategy. Any other
funding mechanisms that emerge during the lifetime of the plan will also be
utilised where appropriate.
15.4.4. It is expected that most infrastructure will be delivered by either the Council or
developers at the beginning or during the build out of development. However,
the Council will work with external partners where necessary to bring forward
infrastructure schemes.
15.4.5. Applicants should discuss infrastructure requirements with the council and
infrastructure providers early in the application process. This allows all parties
to understand the impact of developments, whether any existing capacity exists
or will need to be provided and the costs associated with mitigation.
Developer contributions
15.4.6. Developer contributions play an important part in helping to fund infrastructure
at both the local and strategic level. The established method of collecting
developer contributions is by way of S106 planning obligations. West
Northamptonshire Council has an adopted (June 2026) Infrastructure and
Developer Contributions Supplementary Planning Document (SPD) in place.
Section 106 planning obligations are subject to the tests set out in the National
Planning Policy Framework (paragraph 57) and in Regulation 122 of the
Community Infrastructure Levy Regulations 2010 which require that obligations
are only sought where:
• They are necessary to make the development acceptable in planning
terms;
• Directly related to the development; and
• Fair and reasonably related in scale and kind to the development.
15.5. Infrastructure types
15.5.1. Below are summaries of the types of infrastructure that development is
expected to contribute to. Details on specific schemes to support growth in
West Northamptonshire are contained in the IDP.
Transport infrastructure
15.5.2. Transport infrastructure enables people and goods to move around with modes
including the private car, lorries, walking, wheeling, cycling, taxis and public
transport. Recent years have also seen the emergence of automated shopping
robots as well as electric scooters and e-bikes that can be owned by the
individual or rented.
15.5.3. Off-site schemes will be delivered by a combination of partners including West
Northamptonshire Council, developers, National Highways, Network Rail or
other relevant bodies. The Council also works with sub-national transport body,
England’s Economic Heartland on transport strategies across the region that
impact on the authority. Funding will be secured directly from development
either through Planning Obligations (Section 106), the (Community)
Infrastructure Levy, or other funding sources. On-site schemes will either be
delivered directly by the developer or through S278 agreements.
15.5.4. The placemaking section of this Plan discusses the movement hierarchy in
West Northamptonshire and sets out how developments should prioritise
sustainable and healthy modes such as walking, wheeling and cycling. Policies
within this section should be read in conjunction with other policies in the Plan
and the IDP which sets out the full schedule of transport infrastructure
schemes required to support the proposed growth within this Plan.
15.5.5. The policies within this Plan should be read in conjunction with the West
Northamptonshire Local Transport Plan (LTP), the Electric Vehicles Infrastructure
Strategy (EVIS) and any Local Cycle Walking Infrastructure Plans (LCWIPs)
which are in place. These identify routes which are a priority for upgrading
and/or new routes that development is expected to help deliver. The EVIS sets
out how West Northamptonshire will provide charging infrastructure and
support the transition to decarbonised transport. Any schemes identified in the
LTP, EVIS or LCWIPs will be included in the IDP which will be updated
regularly to reflect new and/or updated schemes.
Social infrastructure
15.5.6. Social infrastructure includes education, healthcare, community, recreation and
sports facilities, and emergency response services. It plays an important role in
maintaining existing and developing new communities and encourages social
and physical links between them.
15.5.7. Development or regeneration proposals can provide opportunities to consider
how facilities are constructed and services are delivered. Colocation of services
should be considered where appropriate to maximise the use of the land and
buildings. Applicants should consult with the Council prior to submitting
applications to discuss master planning and infrastructure requirements
relating to major and strategic sites.
Education
15.5.8. Educational infrastructure includes early years, primary, secondary and special
education and disability schools (SEND) as well as higher education facilities
such as colleges and universities and adult education.
15.5.9. A wide variety of providers will deliver this provision across West
Northamptonshire during the plan period. The Council is the Local Education
Authority and is required to provide a sufficiency of school places to meet the
needs of all children of school age. The Council produces a School
Organisation Plan which covers a 5-year period: the current document covers
2018-2023.
15.5.10. All residential proposals will be required to fully mitigate their impact on
educational infrastructure, and in some cases support transport to access
educational infrastructure. Schemes are required to directly deliver or
contribute to school places, classrooms, and schools and/or contribute to the
delivery of other education infrastructure projects identified in the IDP. These
schemes may be on or off-site and where necessary, developers will be
expected to provide the land to accommodate educational infrastructure.
15.5.11. Some adult learning is also provided by West Northamptonshire Council.
Where appropriate, contributions will be sought towards the provision of this
service.
Local Labour Strategies
15.5.12. Some commercial development will be required to either contribute to or
prepare their own Local Labour Strategy. The Council will work with
developers to create a strategy which will benefit the local labour market and
maximise opportunities for economic and social benefits. Further details can
be found in the economy section of this Plan.
Healthcare
15.5.13. The healthcare system in West Northamptonshire is made up of a range of
organisations with different functions including the Department of Health and
Social Care, NHS England (Midlands region), Northamptonshire Integrated
Care Board (ICB) and the NHS trust.
15.5.14. Northamptonshire ICB is a statutory body responsible for local NHS services,
functions, performance and budgets. It is directly accountable to the NHS and
is made up of local NHS trusts, primary care providers and local authorities.
The ICB will work with the council and developers to ensure the assessment of
existing health infrastructure is robust and that mitigation can be secured
which aligns with NHS requirements.
15.5.15. Northampton General Hospital is the major acute healthcare hospital for West
Northamptonshire as well as being the provider of specialist services (cancer,
stroke and vascular care) for the county.
15.5.16. The current NGH site in Northampton town centre is the main focus for the
hospital’s services and there is a masterplan to guide future development. This
includes construction of new ward blocks, operating theatres, car parking and
administrative accommodation.
Community, recreation and sports
15.5.17. Community and leisure infrastructure includes community halls/centres,
emergency services, cultural development such as libraries, museums and
galleries, indoor and outdoor sports provision, open space, burial spaces as
well as public realm.
15.5.18. In large developments it is expected that facilities will be provided directly by
the developer. However, most proposals will need to contribute to schemes
and, in some cases, meet criteria set out in other policies within this Plan such
those relating to sport and open space.
Emergency services infrastructure
15.5.19. The spatial vision of this Plan seeks a thriving economy and vibrant,
sustainable communities and as part of this, communities will require access to
police and fire services. As such, developments will be expected to contribute
to this type of infrastructure.
15.5.20. An increase in population and employment allocations within West
Northamptonshire not only require access to emergency services, but in some
cases specialist equipment such as hydraulic lifts and community/on- site
policing. Additionally, site masterplans should be designed in conjunction with
the emergency services to ensure that road layouts and parking are accessible
for fire appliances.
Waste services infrastructure
15.5.21. The Council has a statutory duty to collect and make arrangements for the
treatment of Municipal Waste. Population growth has an impact on waste
management and recycling. More people and jobs place additional pressure on
these services which are provided by the Council. Contributions are therefore
required to ensure new properties have suitable facilities for waste and
recycling and to enhance existing or provide new facilities to ensure there is
capacity to sustainably manage West Northamptonshire’s residents waste in
the future.
15.5.22. This includes the provision of new bins, suitable space for waste containers
and contributions to improve waste infrastructure such as household waste
recycling centres, waste depots and waste transfer stations.
Utilities infrastructure
15.5.23. Utility infrastructure provides buildings with energy (usually electric and gas),
potable water and water recycling and telecommunications (phone lines and
internet connections).
15.5.24. National Grid Electricity Transmission owns and maintains the electricity
transmission system in England and Wales. National Gas Transmission owns
and operates the high-pressure gas transmission system across the UK.
National Grid distribute electricity within West Northamptonshire and Cadent
distribute gas within the area. Applicants should liaise directly with these
organisations at the outset of proposals.
15.5.25. Anglian Water, Severn Trent and Thames Water provide water services in
West Northamptonshire. Again, direct liaison between applicants and water
and sewerage companies is expected from the inception of proposals to
ensure necessary capacity is available and connections are made.
15.5.26. Proposals for all new development should ensure appropriate infrastructure is
provided during construction that is sufficient to enable all development to be
connected to full fibre broadband without any post development works.