This site allocation covers the Retail Park in Borehamwood Town Centre, a 5.01 ha urban site in public and private ownership with about 20,000 sqm of mainly large-format retail, leisure and health uses and extensive surface parking. It is allocated for comprehensive mixed-use redevelopment, delivering at least 500 new homes in the latter stages of the plan period, with the 20,000 sqm of main town centre uses re-provided. A site-wide masterplan is required, with phasing that keeps a critical mass of retail activity. Constraints include the culverted Borehamwood Brook beneath part of the car park and flood risk.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
HBA6 Retail Park, Borehamwood
Site Address Retail Park Borehamwood
Site
Characteristics
Site Size ha
5.01 ha
Setting
Urban
Ownership
Public and Private
Current Uses The site is comprised of approximately 20,000 sqm of main town centre
floorspace, principally comprised of large-format retail units, together with
leisure and health uses. The site also includes The Grove Surgery, gym
provision, extensive surface customer parking and servicing areas.
How Site was
Identified
Identified through the Council’s Local Plan urban capacity and site-selection
process and assessed through the HELAA.
Planning
Designations and
Site
Considerations
Strategic urban redevelopment site within Borehamwood Town Centre and
forming a substantial component of the proposed Primary Shopping Area; the
culverted Borehamwood Brook/Main River beneath part of the existing car
park; reservoir and other flood risk.
Planning Status No recent relevant planning history.
Indicative
Development
Capacity
500 dwellings
Reprovision of 20,000 sqm of main town centre uses
Timeframe for delivery
Strategic Objectives
B A thriving local economy
C The regeneration of Borehamwood and Potters Bar
E Meet the Borough’s housing needs by delivering homes for everyone
H Responding to the climate emergency
K Securing the timely delivery of infrastructure
Non-Strategic Policy
Site Allocation
14.46 Borehamwood Town Centre Retail Park is allocated for comprehensive mixed-use
redevelopment comprising residential development together with an appropriate
quantum and range of main town centre uses, including retail; and compatible
leisure, employment, health, commercial and community uses. The re-provided
town centre will be supported by new public realm, public open space and green
and blue infrastructure. The site allocation will deliver at least 500 new homes
during the latter stages of the plan period.
14.47 Development must maintain and strengthen the site’s important contribution to the
vitality and viability of Borehamwood Town Centre while transforming its existing
low-density and car-dominated urban form.
Opportunities
14.48 The site forms a substantial part of Borehamwood Town Centre and the Primary
Shopping Area but is currently characterised by single-use large-format retail
buildings, extensive surface parking and a relatively inward-looking urban form.
14.49 Comprehensive redevelopment provides an opportunity to create a more efficient
and sustainable mixed-use part of the town centre while retaining and modernising
its important retail and other town-centre functions.
14.50 Development provides opportunities to deliver a range of regeneration objectives.
These include substantial new housing in one of the Borough’s most accessible
locations; retention and modernisation of important appropriate and compatible
retail, employment, health, leisure and community functions. It will also deliver the
re-establishment of a traditional town centre street and block structure with active
ground-floor uses and residential development above. This will secure the
improvement of physical and visual connections with Shenley Road; the creation of
new east-west and north-south pedestrian and cycle routes through the site; the
substantial reduction in the dominance of surface parking. It will also secure the
delivery of new public spaces, landscaping and urban greening; the enhancement
Year 1-5 Year 6-10 Year 11-17 Beyond Year 17
in the relationship with Borehamwood Brook and explore opportunities for de-
culverting or naturalisation where technically feasible.
14.51 The redevelopment must be planned as a coherent whole rather than as a series
of disconnected redevelopment parcels. The masterplan should establish the
overall spatial and land-use framework, development parcels and phasing,
movement hierarchy, public realm and blue-green infrastructure, building heights
and massing, parking and servicing strategy and infrastructure requirements.
14.52 Given the importance of the existing Shopping Park to Borehamwood’s retail offer,
the masterplan must demonstrate how redevelopment can be phased while
maintaining an appropriate critical mass of retail and other town-centre activity.
Development Requirements
14.53 Development must be planned comprehensively in accordance with Policy DM3
(Masterplans and comprehensive development). A site-wide masterplan must
demonstrate how the allocation will deliver a coordinated mix of residential, retail,
leisure, commercial, health, community and other compatible town centre uses.
14.54 Landowners and other relevant interests must work positively together in preparing
and delivering the masterplan. The lead landowner or developer bringing forward
the site-wide masterplan must demonstrate that reasonable efforts have been
made to undertake positive and meaningful engagement with other landowners,
occupiers and interests whose land is necessary for or may be affected by the
comprehensive redevelopment of the allocation.
14.55 The masterplan must establish the overall spatial framework for the allocation,
including:
• The distribution and relationship of uses;
• Development parcels and phasing;
• The street and movement hierarchy;
• Connections to Shenley Road, Theobald Street and surrounding
neighbourhoods;
• Public realm and open space;
• Green and blue infrastructure;
• Building heights and massing;
• Parking, servicing and delivery arrangements; and
• Infrastructure requirements and their delivery.
• The masterplan must demonstrate how individual phases can be delivered
without prejudicing the comprehensive redevelopment of remaining parts of the
allocation or the achievement of the wider regeneration objectives for
Borehamwood Town Centre.
14.56 The masterplan must use the design-led approach to consider how the capacity of
the site can be optimised to deliver high intensity mixed-use development that
provides positive frontages that address key routes and public spaces. This will
incorporate high-quality and high-density residential, active ground floor frontages
in line with the Retail and Town Centre policies and incorporate new and improved
public realm and open space.
14.57 The masterplan must contain a site-wide design code consistent with policy
HQD1(K) and undergo assessment through the Design Review Panel.
14.58 Greater height and density are appropriate in principle within this highly accessible
town-centre location. Taller elements should be located through the master
planning process having regard to townscape, public realm, movement, daylight
and sunlight, microclimate and transitions to adjoining lower-rise residential areas.
The site is located within the Borehamwood Town Centre Tall Building Suitability
Zone. This identifies a maximum building height of 20-storeys. This is not an
assumed target height, and remains subject to townscape, heritage, microclimate
and amenity evidence.
14.59 Development must retain and strengthen the site’s main town centre function and
re-provide an appropriate quantum and range of retail and other main town centre
floorspace. The amount and type of retail, leisure, health and community
floorspace must be justified against the Retail and Town Centres evidence and the
objective of maintaining town-centre vitality.
14.60 The phasing strategy must demonstrate how an appropriate retail and service offer
will be maintained during redevelopment so that the vitality and viability of
Borehamwood Town Centre is not unacceptably harmed.
14.61 The site must be fully reintegrated with the surrounding street network, with
substantially improved access and permeability between Shenley Road, Theobald
Street and surrounding neighbourhoods.
14.62 Development must establish a hierarchy of new routes through the site, including
strong east-west and north-south pedestrian and cycle connections linking
redevelopment directly with Shenley Road.
14.63 Development must provide positive and active ground-floor frontages within the
Primary Shopping Area and along principal new streets and public spaces.
14.64 A site-wide public realm strategy must deliver new and improved public spaces,
street trees, landscaping, urban greening and high-quality pedestrian
environments and complement wider improvements to Borehamwood Town
Centre.
14.65 The culverted Borehamwood Brook, flood risk and drainage constraints must
inform the masterplan from the outset. The masterplan must investigate
opportunities to de-culvert, naturalise or otherwise enhance the watercourse where
technically feasible and environmentally beneficial. The masterplan should explore
opportunities for Borehamwood Brook to become a positive component of the
public realm and blue-green infrastructure network rather than remaining solely as
buried infrastructure. Developers should work in partnership with the Environment
Agency and engage with them early at pre-application stage, to mitigate against
potential flood risk.
14.66 Applicants should work in partnership with Thames Water to manage surface
water, divert existing sewers where applicable and ensure infrastructure upgrades
are delivered ahead of the site being occupied.
14.67 Development adjoining existing residential areas must provide appropriate
transitions in scale and protect residential amenity.
14.68 Existing health and community facilities, including The Grove Surgery where a
continuing need is demonstrated, must be retained, appropriately re-provided or
relocated to suitable modern accommodation as part of redevelopment.
Development Guidance
14.69 Development should create a new piece of Borehamwood Town Centre rather
than simply rebuild the existing retail park.
14.70 The masterplan should generally establish a street-based urban form, with main
town centre and other active uses concentrated at ground and lower levels and
residential development above.
14.71 A range of building footprints should be provided to accommodate larger-format
retail uses alongside smaller retail, leisure, commercial, health and community
premises. Buildings should be designed to allow adaptation and subdivision over
time.
14.72 Higher development may be appropriate towards the central and more accessible
parts of the allocation, with scale generally stepping down towards sensitive
residential edges.
14.73 Development should prioritise active travel modes over parking and vehicular
access in line with the Local Transport Plan and LCWIP proposals. The
masterplan will include a forward-facing car parking strategy that secures
maximum standards for the site that will secure a shift towards a car-lite / car-free
future.
14.74 Phasing should be integral to the masterplan. Early phases must establish routes,
public spaces and development parameters that enable rather than constrain
subsequent phases.