The human version (we wrote this, not the council)
This site allocation covers Bushey Golf and Country Club on the High Street, a 12.42 ha publicly owned site that has housed leisure, commercial, events and community uses. It is allocated for residential-led mixed-use regeneration of at least 250 homes, with community and cultural facilities, compatible commercial uses and substantial publicly accessible open space. The site is defined as grey belt, and development must keep strategic separation between Bushey and Oxhey. A substantial part of the former estate must stay as permanent open space, and the project ambition is 50% genuinely affordable homes.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
HBUSA8 Bushey Golf and Country Club, High Street
Site Address Bushey Golf and Country Club, High Street, Bushey
Site
Characteristics
Site Size ha Setting Ownership
12.42 ha Urban extension Public
Current Uses Former Bushey Golf and Country Club. Buildings and parts of the site have
subsequently accommodated leisure, commercial, events and community-
related uses
How Site was
Identified
Call for Sites (CFS-2025-149) and HELAA (HEL176)
Planning
Designations and
Site
Considerations
Metropolitan Green Belt and partly previously developed land. Adjacent/near
Bushey High Street and Melbourne Road Conservation Areas, Bushey Rose
Garden Registered Park and Garden and multiple listed buildings. Also
archaeological potential, TPOs, LNRS ACIB, sand/gravel safeguarding,
limited Flood Zones 2/3 and surface-water risk.
Planning Status No recent relevant planning history.
Indicative
Development
Capacity
250 dwellings, commercial and community space
Timeframe for delivery
Strategic Objectives
E Meet the Borough’s housing needs by delivering homes for everyone
F Delivering affordable homes
G Securing a greener Borough
J Healthy and safe communities
K Securing the timely delivery of infrastructure
Non-Strategic Policy
Site Allocation
16.114 Bushey Golf and Country Club is allocated for comprehensive residential-led
mixed-use regeneration comprising at least 250 homes during the plan period. The
delivery of the site allocation will also secure new community and cultural facilities,
compatible commercial uses and substantial publicly accessible open space and
green infrastructure.
16.115 The Borough-wide Green Belt Assessment Stage 2 further considers the site’s
contribution to the purposes of the Green Belt. It concludes that the site is defined
as grey belt. The comprehensive development of the urban extension must
maintain effective strategic separation between Bushey and Oxhey and establish a
durable long-term Green Belt boundary.
Opportunities
16.116 The site is in Council ownership and serves as one of Bushey’s principal
regeneration opportunities. It includes previously developed land that is highly
accessible to a variety of sustainable travel networks. Its redevelopment provides
an opportunity to accommodate a mix of new housing, community and main town
centre uses while retaining a significant area of the wider site as publicly accessible
green space. As a publicly owned site there is an opportunity to deliver a higher
proportion of new dwellings on the site as genuinely affordable homes.
16.117 The Council-led regeneration of the site can create a community and cultural focus
for Bushey. Regeneration can also secure public access through the former golf
course, which was not previously open to the public, strengthen connections to the
High Street and establish a permanent green edge towards Oxhey.
Development Requirements
16.118 Development must be planned and delivered comprehensively in accordance with
Policy DM3. This requires that a site-wide masterplan be prepared demonstrating
Year 1-5 Year 6-10 Year 11-17 Beyond Year 17
how the strategic urban extension will deliver a mix of new homes and other
compatible uses in accordance with the site allocation.
16.119 The masterplan must use the design-led approach to consider how the capacity of
the site can be optimised to deliver high-quality and higher density homes. It must
coordinate housing, community and commercial uses, public open space,
landscape, heritage, movement, infrastructure and phasing across the allocation and
its relationship with the wider Country Club estate.
16.120 A substantial proportion of the former Country Club estate must be retained and
secured as permanent publicly accessible open space and green infrastructure, with
built development focused on parts capable of accommodating development without
unacceptable Green Belt, landscape or heritage harm. Retained public open space
should have a clear long-term stewardship and management arrangement securing
public access, landscape quality, biodiversity and recreation.
16.121 A strong and permanent Green Belt boundary must be established along the
western and south-western edge of the developed area, using Merry Hill Road,
retained woodland, mature vegetation and other permanent landscape features
wherever possible. The landscape framework must maintain a clear transition to the
retained Green Belt and preserve effective visual and physical separation between
Bushey and Watford.
16.122 As a strategic allocation, development proposals must be prepared in accordance
with Policy HQD1(K) and must be supported by a site-wide Design Code prepared in
alignment with the National Model Design Code, or successor guidance. The site-
specific design code will be coordinated with the masterplan required by Policy DM3.
16.123 Development must be phased to ensure the timely provision of the infrastructure
necessary to support the strategic urban extension. The potential improvements that
could be enabled and delivered through the comprehensive redevelopment of the
site are set out as part of the Vision for Bushey. These will be funded through a
combination of developer contributions (inclusive of CIL) and other sources of
funding secured in support of future growth across Bushey.
16.124 The delivery of the strategic urban extension must take account of the flood risk that
affects the site and incorporate Sustainable Drainage (SuDS) and flood risk
attenuation measures into the earliest stages of the layout. Developers should work
in partnership with the Environment Agency and engage with them early at pre-
application stage, to mitigate against potential flood risk.
16.125 Applicants are expected to work with Hertfordshire Ecology (or any successor body
following LGR) and Herts and Middlesex Wildlife Trust to ensure that open space
provision and Biodiversity Net Gain measures incorporate the relevant actions in the
LNRS. Existing TPO trees, woodland and important landscape features must be
retained wherever practicable and integrated with habitat creation, biodiversity net
gain and the LNRS ACIB.
16.126 Applicants and developers are required to carry out necessary geophysical survey
and archaeological evaluation to reveal the archaeological potential of the site.
16.127 Development proposals must consider and respond positively to the significance and
setting of the Bushey High Street and Melbourne Road Conservation Areas, Bushey
Rose Garden Registered Park and Garden and nearby listed buildings. Masterplans
prepared in support of proposals will be informed by the local heritage assets in
terms of how they provide a positive response to scale, massing, landscape and
architectural across the site allocation.
Development Guidance
16.128 Development should provide for complementary and distinctive character areas
across the strategic urban extension that link in with and complement the masterplan
across this site and existing neighbourhoods to the north. The design and layout of
the development should reflect and reinforce the hierarchy of streets and open/green
spaces, with a differentiation in design, density, scale and massing, including a
range of plot sizes and building heights, with reference to Bushey’s established
character. Built development should be concentrated principally towards High Street
and previously developed parts of the site, with scale and density reducing towards
retained open landscape and sensitive Green Belt edges.
16.129 Residential development should generally be between two to four storeys. Localised
increases in height may be used to mark important routes, spaces or community
focal points where this is justified through the masterplan and heritage and
townscape assessment. Buildings meeting the definition of a tall building in Policy
HQD5 will not be supported, as the site is not within a Tall Building Suitability Zone.
16.130 The new main town centre uses must complement the vitality and viability of Bushey
High Street. It should seek to support the community function of the new community
forming on the site rather than create a competing out-of-centre destination.
16.131 Development must provide a new community hub incorporating flexible community
and cultural space and make appropriate provision for arts, education and uses
associated with the Council-led regeneration.
16.132 Affordable housing must be provided in accordance with Local Plan policy, with the
Council-owned site expected to maximise affordable delivery. Ideally developers
should seek to achieve the current project ambition of 50% genuinely affordable
homes.
16.133 Developers should ensure that the new community hub is well located in relation to
the site’s wider open space provision. This is to enable access to the open space
and take advantage of the area around the pond to facilitate outdoor dining and
events. Masterplans prepared in support of proposals should identify other suitable
locations for the community hub, but in all instances it should be located close to
principal walking routes.
16.134 Development should prioritise active travel modes over parking and vehicular access
in line with the Local Transport Plan and LCWIP proposals. Development must
provide substantially improved walking/cycling permeability through the site,
including connections to High Street, surrounding neighbourhoods, Bushey Station
and routes towards Watford, and should investigate a new public route between
High Street and Merry Hill Road. The masterplan will include a forward-facing car
parking strategy that introduces maximum standards for the site that will secure a
shift towards a car-lite/ car-free future.