The human version (we wrote this, not the council)
This policy sets carbon rules to help the Borough become net zero-carbon. Major development must be net zero-carbon, with an on-site cut in carbon emissions of at least 35% beyond the Part L baseline of the Building Regulations 2021 Future Home Standard, and must minimise unregulated emissions. Where net zero cannot be reached on site, developers must pay into Hertsmere's carbon offset fund or provide off-site measures. Payments use a formula with a charge of £100 per year for every tonne of CO2 offset, over an assumed 30 years. Major schemes are encouraged to assess embodied carbon, and must set out their approach in an Energy Strategy.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
SD4 Minimising Greenhouse Gas Emissions
Strategic Objectives
H Responding to the climate emergency
J Healthy and safe communities
Strategic Policy
A To help Hertsmere to become a net zero-carbon Borough development
proposals must be designed to reduce greenhouse gas emissions in operation
and minimise energy demand (annual and peak).
B Major development proposals must be net zero-carbon and:
i. Meet the minimum on-site reduction of carbon emissions of at least 35%
beyond the baseline of Part L of the Building Regulations 2021 Future Home
Standard; and
ii. Calculate and minimise emissions from any part of the development that are
not covered by Building Regulations (e.g. unregulated emissions).
C Where it is clearly demonstrated that the net zero-carbon target cannot be
achieved on-site, development proposals must make contributions to meet the
identified shortfall through:
i. A cash-in-lieu contribution to Hertsmere’s carbon offset fund. Where it can
be demonstrated to the satisfaction of the Council that off-site contributions
are acceptable these will be secured through planning obligations, with
payments in lieu calculated using Table 11.1 (Carbon offset payments in
lieu).; and/or
ii. Appropriate off-site measures where these can be demonstrated to be
deliverable.
Table 11.1 Carbon offset payments in lieu
FORMULA FOR CALCULATING PAYMENTS IN LIEU
(A – B) x C) x D = X
A = Target carbon emissions to meet a 35% reduction onsite
B = Projected onsite contribution to carbon reductions
Explanation
11.21 The Hertsmere Climate Change and Sustainability Strategy (2025 - 2030) sets the
objective for the Borough to become a zero-carbon place by 2050. To meet this
objective and ensure that Hertsmere becomes a net zero-carbon Borough, it will be
necessary for new development to maximise energy efficiency and reduce carbon
emissions.
11.22 The Borough Council has sought to meet the zero-carbon target for all major
developments since 2020; by publishing the Climate Change and Sustainability
Interim Planning Policy Position Statement (2020). That document sought to provide
guidance based on policy available at that time.
11.23 To meet the Borough’s zero-carbon target, the Local Plan requires major
developments to provide an on-site reduction of at least 35% beyond the baseline of
Part L of the Building Regulations 2021 Future Home Standard.
11.24 Embodied carbon refers to the greenhouse gas emissions arising from the
manufacturing, transportation, installation, maintenance and disposal of building
materials. This is distinguished from operational carbon which refers to emissions
C = Charge for every tonne of CO2 required to be offset to meet the target figure
(Hertsmere will charge £100 per year for every tonne of CO2 to be offset)
D = The assumed lifespan of the offset measures (30 years)
A worked example to illustrate the above calculation:
Development A has annual CO2 emissions of 100 tonnes. To meet the policy
requirement the developer needs to reduce this by 35 tonnes, however the
developer is only able to reduce carbon emissions by 30 tonnes onsite, which means
5 tonnes is required to be offset:
((35 – 30) x 104) x 30 = £31,200
D Major development proposals are encouraged to assess embodied carbon
emissions and maximise opportunities to reduce these emissions.
E Details of the approach used to meet the net zero-carbon target must be clearly
set out in an Energy Strategy submitted as part of the Sustainable Design
Statement.
F Development proposals should minimise energy demand of the building(s) in-
use by seeking to achieve the London Energy Transformation Initiative (LETI)
targets for projected Energy Use Intensity (EUI).
arising from building energy consumption. To help ensure that the carbon emissions
are fully accounted for and minimised during the development process, applicants
are encouraged to assess and address embodied emissions through the design-led
approach. Good practice guidance on this element of low carbon design should be
considered and referred to as part of the development process. The Council
encourages the use and application of established and recognised guidance, such as
that prepared by the London Energy Transformation Initiative (LETI). The Council
considers that given Hertsmere’s location within London’s immediate hinterland this
is relevant and appropriate guidance.
11.25 New development is expected to be net-zero carbon and where this is not feasible, it
should get as close as possible to zero-carbon on-site. Off-site contributions will not
normally be considered as an alternative. They will only be acceptable where it is
clearly demonstrated that carbon targets cannot be fully achieved on-site. These
contributions must address any identified shortfall and will be secured by planning
obligations. Off-site provision will be secured through planning obligations with any
payments in lieu calculated using Table 11.1.
11.26 The LETI Climate Change Design Guide sets out a roadmap to zero carbon
development. It recommends the use of an Energy Use Intensity (EUI) metric. The
EUI is an annual measure of the total energy consumed in a building. It is a good
indicator for building performance as the metric is solely dependent on how the
building performs in-use; rather than carbon emissions, which also reflect the carbon
intensity of the grid. EUI can be estimated at the design stage and easily monitored
in-use as energy bills are based on kilowatt hour (kWh) of energy used by the
building. EUI includes all the energy consumed in the building such as regulated
energy (heating, hot water, cooling, ventilation, and lighting) and unregulated energy
(plug loads and equipment e.g. kitchen white goods, ICT/ AV equipment). It does not
include charging of electric vehicles. Development proposals should make
reasonable efforts to reduce energy consumption of buildings in-use, including by
reducing space heating demand. Details should be set out in the Energy Statement,
where appropriate. The EUI targets in Table 11.2 are non-binding and should be used
as a guide to help future-proof development, until such time EUI targets are set out in
higher level policy or Building Regulations.
Table 11.2 Targets for Energy Use Intensity by Building Type 1
Building type Reduce consumption to Reduce space heating
demand to
Minor Residential 35 kWh/m2/year 15 kWh/m2/year
Major Residential 35 kWh/m2/year
Commercial Office 55 kWh/m2/year
Education 65 kWh/m2/year
1 All targets are set out in kilowatt hour (kWh) per metre square (m2) per year by Gross Internal Area
(GIA) and excluding renewable energy contribution. The LETI Climate Emergency Design Guide
should be referred for further information.