The human version (we wrote this, not the council)
This section introduces the allocations chapter and explains housing supply. Supply is made up of completions, commitments, windfalls and new allocations. The council must keep a five-year supply, with a 5% buffer. Government's method raises the Borough's need from 237 to 364 homes a year. Table 7 sets a requirement of 7280 homes plus a 5% buffer, giving 7644. Planning permissions provide 1092 and windfall 1360, leaving 5192 to allocate. Allocations total 5106, and if all sites, pipeline and windfall came forward, completions would reach 7934 by 2045.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
14.1 In order to be able to allocate the right amount of land it is important to understand the
components of supply within the Borough.
Housing Land
14.2 Housing supply is made up of completions (sites already completed), commitments (sites
with planning permission), windfalls (unidentified sites coming forward for development
during the Plan period) as well as new site allocations and proposals.
14.3 The Borough Council has to maintain a 5-year housing supply. The National Planning Policy
Guidance introduced a requirement for either a 5% or 20% buffer depending on whether
the Council has a good record or not of maintaining and delivering a five-year housing
supply. The Borough Council will monitor its housing delivery to ensure that good delivery
is maintained. There is therefore a 5% flexibility included in the five-year housing supply.
14.4 Table 7 indicates the amount of housing that is required for the remaining Plan period.
14.5 The Strategic Housing Land Availability Assessment 2016 indicated that there is was
sufficient land to cater for the housing requirement up to and beyond 2031. Whilst North
Warwickshire continues to be constrained by the Green Belt and infrastructure bottlenecks,
there is still sufficient land within the Borough to build homes. However, targeting where
these homes will go to the most sustainable locations is a critical issue. In addition, the
Borough Council has historically and still seeks to actively pursue development on land it
owns as well as County Council owned land to ensure the continuous supply of readily
available sites. Specific allocations are brought forward through this Plan. Additional sites
could be brought through a Neighbourhood Plan.
14.6 The Government has announced a new methodology for assessing housing need. In the
accompanying spreadsheet North Warwickshire’s housing need goes up from 237 to 364
dwellings per annum. However, this does not take account of the duty to co-operate in
respect of both Coventry and Birmingham. The figure from Coventry, for example, takes
the overall reduction down to 820 over the plan period or 54 per annum.
Table 7: Housing Supply
a Housing Requirement As expressed in LP5 7280
5% buffer = 364 = Total Requirement 7644
Part A - Pipeline
b Planning permissions as at 01/04/2025 1126 minus 3% for lapse rate 1092
c Windfall Allowance An allowance of 80 dwellings per
annum from 2028/29 to 2044/45
1360
d Sub-total of supply b + c 2452
Part B - Outstanding Requirement
e Outstanding Requirement Land to be allocated 7644 – d 5192
Allocations:
Housing and reserve housing
allocations from NWLP 2021 to be
carried forward as housing allocations
(H2, H3, H4, H7, H8, H10, H11 &
H30/ formerly RH1, H32/ formerly
RH2, H28/ formerly RH3
4,156
Housing allocations and reserve
housing allocations from NWLP Plan
2021 placed into reserve status
(Part H9(RH9), RH10 & RH11) 376
New Housing Allocations as part of the
Local Plan Review - listed in LP37
H12, H13, H15 to H19, H21 to H23,
H26, H27, H29, H31, H33 to H35 @
35 dwellings per hectare
950
Total Supply 5482
14.7 The housing allocations are listed in LP37. These total a figure of 5106. This assumes
30 dph for the housing allocations and reserve sites that have been carried forward from
the Local Plan 2021 and 35 dph for all new sites. Utilising a higher density will maximise
land use efficiency and will allow the Council to achieve its housing requirement without
having to develop larger amounts of greenfield and Green Belt land. This means if all sites
were delivered and all pipelines and windfalls came forward total completions would be
7934 by 2045. The range of sites provides added flexibility.
14.8 The number of new housing and its delivery alongside the relevant infrastructure will be
challenging. The Borough Council will work with funding agencies and organisations
particularly the Local Enterprise Partnerships and the Combined Authority to access
additional funding.