The human version (we wrote this, not the council)
This policy supports a network of waste facilities that manages waste as high up the waste hierarchy as practical and meets identified needs. New or extended waste, recycling and recovery facilities will be supported if they meet a set of criteria. These include reuse or recycling of waste, low greenhouse gas emissions, suitable location and scale, and safe access to roads. Proposals must avoid unacceptable effects such as noise, dust, odour, litter and flood risk, and must not harm the safe operation of Birmingham Airport. Green Belt proposals will be judged against the NPPF. Expanding and modernising the existing HWRC at Bickenhill is supported in principle.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
Policy SMBC/WM1: Waste Management Facilities
1 The Council will support the development of an efficient and sustainable network of
waste management infrastructure which enables waste to be managed at the highest
practicable level of the waste hierarchy, contributes towards a circular economy and
provides sufficient capacity to meet identified waste management needs.
2 Proposals for new waste management, recycling, recovery and processing facilities, or
for the extension or intensification of existing facilities, will be supported where the
following criteria are satisfied:
A The proposal contributes to an appropriate network of waste management
facilities and, where relevant, addresses an identified need for additional or
replacement waste management capacity;
B Facilitates the beneficial reuse, recycling or recovery of waste and, where
appropriate, the production and use of secondary and recycled materials;
C The design and operation of the facility should incorporate appropriate climate
change adaptation measures that minimise greenhouse gas emissions;
maximise resource and energy efficiency and facilitate the recovery and
beneficial use of materials. Where practicable opportunities to utilise any heat
or energy generated on site should be incorporated into the development.
D Where a proposal is situated within the Green Belt, it will be considered in
accordance with the policies of the NPPF . Particular regard will be given to the
specific locational requirements of the proposed waste management activity;
any existing onsite activity of a similar nature; and to whether a suitable
alternative location outside the Green Belt is reasonably available.
E The location and scale of the development must be appropriate to the
proposed waste management activity. Particular support will be given to
proposals which make effective use of: existing waste management sites;
previously developed land; and/or land or b uildings within established
employment or industrial areas where the proposed activity is compatible with
neighbouring uses.
F T h e r e i s s a f e a n d s u i t a b l e a c c e s s t o t h e h i g h w a y n e t w o r k a n d t h e v o l u m e ,
nature and routing of traffic generated can be satisfactorily accommodated
without unacceptable effects on highway safety, congestion, residential
amenity or the environment. This should have regard to operational hours and
associated vehicle movements.
G The proposal must demonstrate that it would not result in unacceptable
effects upon local communities, sensitive receptors or the environment,
including from: noise and vibration; dust, fumes and other emissions to air;
odour; litter; vermin, insects or bi rds; artificial lighting; visual intrusion; land
contamination or instability; effects upon surface water or groundwater; and
flood risk.
H The proposal must be capable of being satisfactorily integrated into its
surroundings and must achieve a high standard of design appropriate to its
context and function. This should include the appropriate consideration of
landscape, ecology and heritage matters in accordance with the policies of
this Local Plan, any respective Neighbourhood Plan and the NPPF .
I The proposal should demonstrate that aviation safety and the safe operation
of Birmingham Airport would not be adversely affected.
3 When considering the above points, the Council will have regard to the type and scale
of the facility and the potential for impacts to occur throughout construction,
operation and, where relevant, restoration.
4 Opportunities to expand and modernise the existing HWRC at Bickenhill will be
supported in principle. The detailed design of the new facility will be considered
against the appropriate criteria set out in part 2 of this policy. The site is considered to
already satisfy the location requirements of part 2D of this policy.
5 Where the development is temporary, or where restoration will ultimately be required,
proposals must provide for the timely restoration and appropriate after-use of the site
to a high environmental standard. Where necessary, satisfactory arrangements for
implementation, aftercare and long-term management will be secured by condition.