This policy says all development should be energy and resource efficient and take a fabric first approach, building in energy saving from the start. New homes should use no more than 110 litres of water per person per day, falling to 100 litres by 2030 and 80 litres by 2035. Non-household schemes should aim for at least 3 credits under BREEAM measure WAT01. New buildings must meet future homes and building standards, cut energy demand first, then add renewable energy. Energy upgrades to existing buildings are encouraged if heritage is not harmed. Proposals must show how they reduce embodied carbon, putting reuse of existing buildings first.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
Policy DM9.1: Sustainable Design and Construction
1. All development proposals should be energy and resource efficient, and should take a fabric first approach to design, whereby energy efficient
measures are considered at the outset.
Water Efficiency
2. All new residential developments should achieve a progressive water efficiency standard of 110 litres per person per day+, reducing to
i. 100 litres per person per day by 2030; and
ii. 80 litres per person per day by 2035.
3. Non-household development should aim to achieve a minimum of 3 credits under the BREEAM New Construction Standard measure WAT01.
Energy Efficiency
4(a) Energy Efficiency in new developments:
New developments must comply with future homes and building standards and must take a ‘fabric first’ approach to building design, embedding
the energy hierarchy, by improving building fabric standards and energy efficiency to ensure energy demand is minimised, then installing
renewable energy generation capacity to meet or exceed demand where possible, and if required, offsetting any residual energy demand.
Factors that influence energy demand and renewable energy potential should be taken into account at the design stage, for example orientation,
built form, building fabric, site layout and landscaping measures.
4(b) Energy efficiency improvements to existing buildings:
Energy efficiency and low carbon heating measures undertaken as part of the redevelopment of existing buildings and structures will be
encouraged where they would not harm heritage assets or their setting.
Embodied Carbon
5(a) Reducing embodied carbon in new developments. All development proposals must demonstrate the measures taken to minimise embodied
carbon (subject to meeting net zero in operation requirements first) and how circular economy principles have been embedded into the design. In
doing so:
i. Priority should be given to re-using, renovating or retrofitting existing buildings and/or structures on a site and demolition will only be
acceptable where justified to the satisfaction of the Local Planning Authority.
ii. Proposals for all new residential and non-residential buildings must demonstrate that upfront embodied carbon* has been considered and
reduced as far as possible through good design and material efficiency.
+ Includes 5 litres per person per day for external water consumption (garden use)
*Upfront Embodied Carbon = emissions associated with the Building Life Cycle Stages A1-A5 and RIBA stages 2/3, 4 and 6)
Energy – development management policy
Reference to Strategic Objective and Strategic Policies
Strategic Objective 15 Strategic Policy SP9
Why we need this Policy
● The UK currently uses approximately three times more energy than the
electricity grid can produce, the balance being met by fossil fuels such
as gas.
● There is limited capacity within Southend for large scale on or offshore
wind or solar power generation, due to the densely built-up character
of the city, and the environmental designations along the foreshore
which protect internationally important bird species However, Micro-
generation131 within individual development sites, including solar
panels, and air or ground source heat pumps could make a significant
contribution to renewable energy generation within Southend.
● The electricity grid in Southend is constrained, due in part (at least)
to its coastal location at the very edge of the electricity grid and an
increasing population will lead to increased demand for power, along
with transition from gas boilers for domestic use during the plan period.
● There is limited potential for local heat networks within the existing
built-up area of the city due to lack of space for heating plant or
energy centres 132.
● Local or community energy (battery) storage can help to ensure local
energy resilience and harness local renewable energy generation.
131 Microgeneration of renewable energy is often permitted development and therefore may not require planning permission, although it is advisable to check before installing anything.
132 https://assets.publishing.service.gov.uk/media/5abccf5f40f0b6026d7ecefb/HNIP_What_is_a_heat_network.pdf
133 https://www.utilitybidder.co.uk/blog/solar-sunlight-index/
134 Past Projects – Climate Change https://www.southendclimateaction.co.uk/projects/projects-1
Zero carbon developments achieve no net emissions by reducing
carbon emissions by on-site, inclusion of renewable energy
generation and balancing any imports with exports to the National Grid
to achieve a zero balance. Low carbon developments are similar but
generally achieve at least a 50% reduction in the energy use of new
buildings. Making more effective use of energy resources including
the potential for renewable energy generation on site is a high priority
for Southend in order to transition away from fossil fuels and towards
zero carbon.
9.18 Compared to the national average Southend benefits from a higher-
than-average amount of sunlight 133 with solar power providing a
good option to harness this. Community batteries are increasingly
being seen as a way of harnessing local renewable energy
generation from solar and micro-wind turbines and enabling the
sharing of more solar within the local area, including to households
without solar, and help to overcome a lack of local network
capacity. Local battery storage can help to regulate voltage on the
network and improve network quality and resilience and enable
carbon emission reductions by storing renewable energy and
making it available at times of peak demand, reducing the reliance
on non-renewable energy sources.
9.19 The REMeDY project134 developed by Southend-on-Sea City
Council’s climate team and partners, promotes the use of communal
heat networks, a mix of communal solar panels and battery storage
and potentially communal wind, to deliver low carbon heat and
power. This approach is best suited to denser new build, flatted
residential developments, where space is limited for heat pumps.
It identifies local heat network priority areas in the City Centre and
Westcliff.
9.20 Nearly a fifth of carbon emissions in the city are from transport
(industries and households) 135, and action to help address carbon
emissions arising from the use of petrol and diesel vehicles is
expected to have positive local effects; supporting the use of
electric vehicles is a key part of this. There are already several
charging points for electric vehicles across the city, available for
the public to use for a fee. However, with the number of electric
vehicles increasing, and in the context of the UK’s net zero
emissions targets, there is opportunity to enhance the provision
of electric vehicle charging across Southend, and public charging
points will be encouraged in appropriate locations, such as
commercial/ retail Centres, and where they serve a local need.
How the Policy Works
9.21 The Council will work in partnership with energy service companies,
property owners and other partners with the objective of delivering
decentralised and low carbon energy within the city where possible.
Community projects to increase local energy resilience will be
encouraged.
9.22 Where development takes place on greenfield sites, and at scale,
there will be much greater opportunity for on-site renewable
135 Southend-on-Sea City Council – Electric Vehicle Charging Infrastructure for new development Supplementary Planning Document (2021) https://www.southend.gov.uk/development-plan-documents/electric-vehicle-
charging-infrastructure-new-development-supplementary-planning-document-adoption
136 Southend-on-Sea City Council – Electric Vehicle Charging Infrastructure for new development Supplementary Planning Document (2021) https://www.southend.gov.uk/development-plan-documents/electric-vehicle-
charging-infrastructure-new-development-supplementary-planning-document-adoption
137 Infrastructure for charging electric vehicles: Approved Document S - GOV.UK
energy generation and supply, and applications will be required to
demonstrate that this has been considered as an integral part of the
development.
9.23 Developments of 50 or more residential dwellings will be
expected to demonstrate that they have explored the potential
benefits of delivering heat through an energy masterplan. Being
able to connect to a heat network at a future date means that the
development would be optimally designed to connect to a district
energy network upon construction or at some point afterwards.
9.24 Since 2021 Southend has applied its Supplementary Planning
Guidance136 to achieve provision of electric vehicle charging
spaces in new residential and commercial development (where car
parking spaces are provided). This has succeeded in increasing
the amount of charging spaces in the city, and the requirement has
been incorporated into Policy DM9.2. In 2023 this requirement was
confirmed in Building Regulations Part S. 137
9.25 Applications for mixed use development will be considered on a
case-by-case basis but as a general principle where car parking
is allocated solely in association with residential properties the
residential EV charge point standard will apply. Spaces should be
rounded up to the nearest whole number e.g. 3.6 spaces would be
rounded up to 4 spaces.