The human version (we wrote this, not the council)
This site allocation covers land east of the A43 in Northampton, allocated for residential development. A masterplan agreed by the Council must show comprehensive delivery. Proposals must provide approximately 1,950 dwellings, open space and sports provision, education, and a new local centre. They must also provide a mobility hub, green corridors linking to Cowpasture Spinney, and full integration with the Northampton North SUE. Green buffers must keep a clear rural-urban transition and protect villages such as Overstone, Moulton and Sywell. Healthcare and transport contributions are required, and impacts on the Upper Nene Valley Gravel Pits Special Protection Area must be addressed.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
Policy N16 – Northampton, East of the A43
Site N16 is allocated for residential development.
A. Proposals for this site must be informed by a Masterplan agreed by the Council that
must demonstrate how the site can come forward comprehensively.
B. Proposals for this site will make provision for all of the following:
i. Approximately 1,950 dwellings;
ii. Development which is consistent with the diagram shown in Figure 12;
iii. Appropriate open space/sports provision, education provision, and a new local centre
incorporating appropriately scaled retail, community, health and other supporting
infrastructure within comfortable walking and cycling distances, as identified through
the Strategic Transport Assessment;
iv. A mobility hub to facilitate a sustainable and integrated transport network,
incorporating safe and direct walking, wheeling, cycling and public transport routes
with strong connections to nearby neighbourhoods, the town centre and surrounding
green corridors;
v. An integrated network of public open space, play areas and green corridors connecting
to Cowpasture Spinney and the wider countryside;
vi. Structural greenspace and wildlife corridors which retain important existing landscape
features including hedgerows, drainage corridors, woodlands and mature trees and
include appropriate landscape enhancements in keeping with the Landscape Character
Type;
vii. Full integration with the Northampton North SUE, including coherent access, layout
and design;
viii. Retained and reinforced green infrastructure buffers to maintain a clear rural-urban
transition and to protect the character of the surrounding countryside and villages such
as Overstone, Moulton and Sywell;
ix. Appropriate healthcare infrastructure contributions, which may include financial
contributions or new primary care infrastructure. Where necessary, land may be
required;
x. An appropriate contribution towards off site sustainable transport and highways
mitigation measures as set out in the Local Plan’s Strategic Transport Assessment
(2026), and
xi. Upper Nene Valley Gravel Pits Special Protection Area impacts, including the
requirement for sensitive design to avoid the displacement of birds due to operational
activity and the demonstration of compliance with the requirements of Policy EN15.
C. Proposals for the site will be informed by assessments and suitable mitigation related
to:
i. Archaeological and heritage impact: A heritage and archaeological assessment,
addressing potential effects on known or potential assets and the setting of
surrounding villages;
ii. Landscape and visual impact;
iii. Ecological impact;
iv. Highways and transport;
v. Flood risk considering the Plan’s Strategic Flood Risk Assessment;
vi. Water recycling infrastructure;
vii. A noise and air quality assessment, identifying and incorporating mitigation for
potential impacts from the A43;
viii. Crime and disorder; and
ix. Minerals and waste.
D. Prior to submission, two years of overwintering bird surveys shall be undertaken to
determine whether the site is used by overwintering Golden Plover / Lapwing and to
identify whether it acts as functionally linked land to the Upper Nene Valley Gravel Pits
Special Protection Area. If the site is found to be functionally linked land, appropriate
mitigation will be required for the loss of habitat and the application accompanied by a
Construction Environmental Management Plan (CEMP) that includes measures that avoid
the displacement of protected birds from construction noise and construction activity
including, where appropriate, restrictions on the timing of works.
WNLP Objectives: 1, 9, 10, 12
Figure 12: Development principles for Northampton, East of A43 (N6xvii)
Northampton, Northampton West (Remaining) (N6xviii)
5.9.55. The Northampton West Sustainable Urban Extension (SUE) was originally
allocated in the WNJCS as one of eight strategic growth locations intended to
accommodate a balanced mix of housing, community facilities, green
infrastructure and sustainable transport links. Within the northern part of the
allocation several parcels have gained planning permission, with some now
completed or under construction. The southern part of the SUE, located south of
Roman Road, has not progressed as anticipated. To maintain a coherent
approach to the growth at the western edge of Northampton and ensure the
delivery of the reminder of this strategic location, the remaining land within the
original allocation which doesn’t yet have the benefit of planning permission, is
reallocated in this Local Plan. This will secure a policy framework for the site,
enabling the delivery of a high-quality, sustainable neighbourhood.
5.9.56. The original Northampton West SUE occupies land on the western edge of
Northampton, adjoining the established residential neighbourhoods of Duston
and New Duston. The site presents a varied rural-urban interface. The village of
Harpole lies in close proximity to the south, accessed via Upper High Street,
while open countryside extends to the west. To the north and east, the site
adjoins land forming part of Northampton West SUE. Development proposals
should have regard to the Harpole Conservation Area Appraisal, particularly in
relation to the contribution made by the surrounding landscape, field patterns,
hedgerows and open setting to the significance of the Conservation Area.
5.9.57. The landscape character of the site is defined by its gently undulating
topography, lower-lying landform and transitional edge-of-town setting. The
Northampton Landscape Sensitivity and Green Infrastructure Study identifies this
area as being of low to medium landscape sensitivity, making it capable of
accommodating change providing that development responds positively to local
landforms, views and settlement edges. Much of the land sits within the lower
parts of the local topography, with the 115m contour marking a notable change
in landform. This contour also provides a natural threshold that helps preserve
the setting and separation of nearby villages, including Harpole, and will
continue to inform the extent and form of development.
5.9.58. There are no designated heritage assets or strategic floodplain constraints
affecting the site. Ecological interest is generally limited due to the
predominance of arable land, hedgerows, ditches and woodland edges provide
opportunities to reinforce and extend habitat networks. Green infrastructure and
habitat creation will therefore play a central role in delivering biodiversity
enhancements and integrating development into the wider landscape.
5.9.59. The North West Bypass has been constructed on the eastern side of the site,
providing a strategic connection from A4500 through New Sandy Lane to A428
Harlestone Road and A5199 Welford Road, significantly improving vehicular
movement and network resilience in this part of the area. The presence of the
completed road now influences access arrangements, traffic distribution and
opportunities for sustainable travel within the reallocated site.
5.9.60. Green infrastructure plays a critical role in shaping the character and form of the
southern part of the Northampton West SUE. The site sits within a transitional
landscape where the western edge of Northampton meets open countryside and
the smaller rural settlement of Harpole. This edge-of-settlement context requires
careful design to maintain the distinct identity of surrounding villages and to
ensure new development is visually and physically well integrated into its
landscape setting.
5.9.61. A key feature of the local spatial framework is the Green Wedge separating
Harpole village from the allocation site. This long-established wedge forms an
important break in development, preserving the open rural setting of Harpole,
safeguarding its historic village form, and preventing coalescence with the
expanding urban area of Northampton. The Green Wedge also provides
opportunities for enhanced biodiversity, recreational access and landscape
buffering.
5.9.62. Across the wider site, opportunities remain to enhance green infrastructure
through new habitat corridors, improved connectivity to existing rights of way,
and integration with open spaces and structural planting within the implemented
parts of the wider Northampton West SUE. These elements are essential to
ensure development is visually assimilated into the surrounding landscape and
contributes to long term ecological resilience.
5.9.63. The scale of planned growth in the western area of Northampton means that
delivery is expected to progress in a coordinated and phased manner across
multiple parcels and developers. This approach allows housing output to be
managed effectively while ensuring that supporting infrastructure, community
facilities and green spaces come forward at the right time. The southern part of
the SUE is well placed to contribute positively to this wider programme of
growth, building on existing momentum and benefitting from the infrastructure
foundations already in place.
5.9.64. The site includes land within a Mineral Safeguarding Area and is in proximity to
existing and proposed minerals and waste facilities. Development proposals
should demonstrate compliance with relevant Minerals and Waste Local Plan
policies.
5.9.65. A comprehensive masterplan will guide the remaining development, ensuring
coherence with earlier phases and providing clarity on design quality, green
infrastructure, sustainable transport and community needs.