This site allocation covers land south of Junction 15 of the M1, allocated for 68 hectares of strategic warehousing. A masterplan covering the whole site must be prepared before any planning application. Two years of overwintering bird surveys are needed, and impacts on the Upper Nene Valley Gravel Pits Special Protection Area must be addressed. The design must reduce the effect of building scale and massing on local character. A strategic landscape assessment is required, respecting the setting of the Courteenhall registered park and garden. A detailed heritage impact assessment, agreed with Historic England, and a detailed ecological assessment are also required.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
Policy N23 – Northampton, South of Junction 15 M1
Site N23 is allocated for 68 Ha of strategic warehousing development.
A. An integrated, coordinated and comprehensive planning approach will be taken for the
site and a masterplan must be prepared, in consultation with the local planning authority
and the local highway authority, and other statutory undertakers prior to the submission
of a planning application covering the development of the whole site. This should include
consideration of impacts on the Upper Nene Valley Gravel Pits Special Protection Area,
including the requirement for sensitive design to avoid the displacement of birds due to
operational activity and the demonstration of compliance with the requirements of Policy
EN15
B. Prior to submission, two years of overwintering bird surveys shall be undertaken to
determine whether the site is used by overwintering Golden Plover / Lapwing and to
identify whether it acts as functionally linked land to the Upper Nene Valley Gravel Pits
Special Protection Area. If the site is found to be functionally linked land, appropriate
mitigation will be required for the loss of habitat and the application accompanied by a
Construction Environmental Management Plan (CEMP) that includes measures that avoid
the displacement of protected birds from construction noise and construction activity
including, where appropriate, restrictions on the timing of works.
C. The proposed development should be designed in a manner which will reduce the impact
of the scale and massing of the buildings on the local character of the area.
D. A detailed strategic landscape assessment of the whole site will be required to deliver a
high quality landscaped setting within and around the boundary of the proposal. The
assessment needs to demonstrate how the scheme will respect the undulating character
of the landscape and the setting of the Courteenhall registered park and garden.
E. A detailed heritage impact assessment will be required for the whole site, to be agreed
with the Local Planning Authority in consultation with Historic England, prior to the design
of the scheme in order to inform the height of any proposed buildings, layout and extent
of the development. This will explicitly include an assessment of the height of any new
buildings and impact on the Courteenhall Registered Park and Garden as well as detailed
consideration of any impacts on designated and non- designated heritage assets. Subject
to the assessment being agreed, a programme of informed mitigation should be included
with any application.
F. A detailed ecological assessment will be required to identify sensitive ecological receptors.
Including an appropriate suite of habitat and species surveys carried out, suitable
mitigation measures identified, and an appropriate assessment of Biodiversity Net Gain
within the site design making suitable BNG provisions on site with a view to achieving
LNRS measures.
G. Proposals will be required to be supported by a detailed Transport Assessment that
includes consideration of the impact of the scheme, including cumulative impact, on the
A45, A508 and the M1.
H. Proposals will be required to make an appropriate contribution towards off site
sustainable transport and highways mitigation measures as set out in the Local Plan’s
Strategic Transport Assessment (2026).
I. Subject to detailed assessment (including an assessment of contaminated land),
development on this site should maximise the use of Sustainable Drainage Systems
(SuDS) to reduce the rate of surface water run off.
J. Any proposal for this site should be accompanied by a site-specific Flood Risk
Assessment. Any proposal should also take into account the fact that the site is included
within the Upper Nene Catchment Local standards for surface water drainage of 1 in 200
year plus an allowance for climate change to protect against pluvial flooding.
WNLP Objectives: 7, 10, 14, 15
Figure 19: Development principles for Northampton, South of Junction 15, M1