This policy sets out how development must manage flood risk. Proposals must apply a sequential approach, not increase flood risk, leave an undeveloped setback from watercourses, and stay safe and operational in a flood. A site-specific Flood Risk Assessment is required in Flood Zones 2, 3a and 3b, for all major development in Flood Zone 1, and elsewhere where other flood sources may affect a site. Schemes passing the Sequential and Exception Tests must put vulnerable uses in the lowest risk areas, avoid net loss of flood storage and include safe access and egress. A Flood Emergency Response Plan is required where appropriate.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
SD7 Minimising and Managing Flood Risk
Strategic Objectives
H Responding to the climate emergency
J Healthy and safe communities
K Securing the timely delivery of infrastructure
Strategic Policy
A In those circumstances where it is necessary to minimise and manage flood risk
proposals for development must:
i. Apply a sequential approach to the location of new development to avoid
flood risk to the population and property whilst taking account of the long-
term impact of climate change;
ii. Not increase flood risk and reduce the risk of flooding from all sources;
iii. Make space for water by providing an undeveloped setback from rivers and
other watercourses;
iv. Where appropriate, carry out a condition survey of flood defence and other
watercourse infrastructure and if necessary, provide for maintenance, repairs
or remediation to secure its functional integrity over the lifetime of the
development; and
v. Be designed to remain safe and operational under flood conditions.
B A site-specific Flood Risk Assessment (FRA) will be required for all relevant
development proposals within Flood Zone 2, 3a and 3b, all major development
in Flood Zone 1, and elsewhere in the Borough where development may be at
risk of other sources of flooding. The FRA must provide sufficient information for
the Council to assess whether the requirements of the Sequential and Exception
Tests have been satisfied. In circumstances where it is required the FRA must:
i. Be proportionate with the degree of flood risk posed both to and by the
development;
ii. Take account of all potential sources of flooding both on and off-site;
iii. Make an appropriate allowance for the hazard posed by climate change over
the lifetime of the development; and
iv. Have regard to the recommendations of the latest Hertsmere SFRA and
Local Flood Risk Management Strategy.
C Where development proposals are required to satisfy the Sequential and
Exception Tests, they must be designed to ensure that:
i. The most vulnerable land uses are directed to areas of the site that are at
lowest risk of flooding;
ii. There is no net loss of flood storage capacity and adequate provision is made
for flood storage and compensation, with priority given to on-site provision;
iii. There is no detrimental impact on the natural function of the floodplain and
floodwater flow routes across the site; and
iv. Appropriate mitigation measures are incorporated to address any residual
flood risk, including safe access and egress for all likely users of the
development.
D Development proposals must provide a site-specific Flood Emergency Response
Plan to manage actual and/or residual flood risk, where appropriate.
Figure 11.1: Hertsmere Flood Zones and Critical Drainage
Explanation
11.47 Hertsmere’s most significant main rivers are the River Colne and Mimmshall Brook.
The River Colne has the widest floodplain, with the watercourse forming the
boundary between Watford and Bushey in the east. The Mimmshall Brook flows
through a largely rural part of the Borough and is subsequently not a major flood risk
to people and property.
11.48 Other noteworthy watercourses include the Radlett Brook, otherwise known as Tykes
Water, which runs through the centre of Radlett. Its course is largely protected by a
flood storage area at the upstream end of the town. The most recent Strategic Flood
Risk Assessment (Level 2 June 2026), notes that the Environment Agency dataset
Recorded Flood Outlines2 notes that fluvial flooding has also been recorded along
the Tyke’s Water in Radlett.
11.49 Elsewhere there are localised areas across Hertsmere that are at potential risk from
other sources of flooding including through surface water run-off, ground water
flooding, surcharge from the sewer network and the blockage of culverts and gullies.
11.50 New development must not increase flood risk to people and properties.
Development proposals should proactively seek to minimise and mitigate flood risk
by considering risk from all sources using appropriate and up-to-date information.
Early engagement with relevant stakeholders, including the Hertfordshire County
Council as Lead Local Flood Authority, the Environment Agency (EA), Thames Water
Utilities and Affinity Water is strongly advised.
11.51 The Council regularly reviews the Hertsmere Strategic Flood Risk Assessment
(SFRA), they are intended to be living documents which are kept up to date as
information on flood risk management changes. The purpose of the Level 1 SFRA
(2023) is to collate and analyse the most up to date readily available flood risk
information for all sources of flooding and provide an overview of flood risk issues
across the Borough. The Level 1 SFRA considers the risk of flooding now and in the
future because of climate change. It maps the Borough into flood zones according to
the probability of flooding occurring, discounting the presence of any flood defences
and alleviation measures.
11.52 Flood Zone 3b is the functional floodplain, where water must flow or be stored in
times of flood. Applicants should consult the Environment Agency (EA) for site
specific flood model outputs to better understand flood risk, and to establish whether
the flood zones in the SFRA have been updated.
11.53 In line with national planning policy a sequential approach must be used to ensure
that new development is directed to those areas of the Borough, and locations within
sites, that are at the lowest risk of flooding. We will consider the appropriateness of
development having regard to the Sequential and Exception Tests, and FRAs
2 Environment Agency Recorded Flood Outlines https://www.data.gov.uk/dataset/16e32c53 -35a6-
4d54-a111-ca09031eaaaf/recorded-flood-outlines (Accessed August 2025)
submitted by applicants. FRAs must consider the long-term hazard posed by climate
change. The latest standing advice on climate change allowances published by the
EA should be referred and form the basis of assessments.
11.54 The Council has also prepared and published a Level 2 SFRA (June 2026). That
document considers the detailed nature of the flood characteristics within a flood
zone including, where possible flood probability; flood depth; flood velocity; rate of
onset of flooding; and duration of flood. This enables users to apply the Sequential
Test by identifying the severity and variation in risk within medium and high flood risk
areas for all sources of flood risk; establish whether proposed site allocations or
windfall sites, on which the emerging Local Plan will rely, are capable of being made
safe throughout their lifetime without increasing flood risk elsewhere; and begin to
consider the application of the Exception Test, where it is relevant.
11.55 National planning policy states that the Exception Test may be satisfied where
development provides wider sustainability benefits to the community that outweigh
flood risk. This will be considered on a case-by-case basis however all such
development must be demonstrably necessary to support the delivery of the spatial
strategy, for example, community or other types of infrastructure.
11.56 As part of the plan-making process the Council has undertaken a Sequential Test to
assist in the site allocation selection process. Allocated sites that have passed the
Sequential Test will not need to apply this test again, unless the proposed use is not
consistent with the site allocation.
11.57 Where the Sequential and Exception Tests are satisfied development proposals must
fully investigate opportunities to avoid, reduce, manage and mitigate flood risk
through site layout and development design. This includes appropriate measures to
ensure development is safe. Proposals should fully assess and address residual risk,
including through flood resistant design (e.g. to prevent water from entering the
building and damaging its fabric) and resilient design (e.g. to ensure the building’s
structural integrity is maintained and that drying and cleaning can be facilitated).
11.58 In circumstances where it is relevant and necessary proposals for development must
be accompanied by a Flood Emergency Response Plan to ensure safe access and
egress from actual and/or residual flooding, where appropriate. This measure is
necessary to ensure that building occupiers can be made aware of the responses to
various types and scale of flood threat, evacuation logistics, evacuation routes and
other safety arrangements in terms of dry access, egress and refuge. Examples of
such developments can include proposals with water compatible uses, alterations to
existing buildings and building floor levels that have been raised, but where there is
remaining flood risk under the 0.1% AEP event.