This policy says major development is expected to provide, or pay towards, measures that reduce its impact, plus the infrastructure it needs. The Council may use planning obligations, pool contributions and collect the Community Infrastructure Levy. Schemes that cannot meet policies on viability grounds need a detailed Viability Assessment. The text explains contributions for education, healthcare, sports hubs, public transport, travel plans and police. Sports hubs are planned to serve Balsall Common, Blythe, East of Solihull and Knowle. From the last quarter of 2024 to mid-2026, at least 14 major schemes for up to 3,700 dwellings were approved, with up to £44 million in commuted sums.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
Policy SMBC/D2: Infrastructure Provision and Developer
Contributions
1 Major Development will be expected to provide, or contribute towards, provision of:
A Measures to directly mitigate its impact and make it acceptable in planning
terms
B Physical, social, green and digital infrastructure to support the needs
associated with the development.
2 Infrastructure and mitigation measures will be provided in a timely manner to support
the objectives of the Local Plan.
3 The Council will, where appropriate, seek to secure site-specific measures through
planning obligations. The nature and scale of any planning obligations sought will be
related to the form of development and its potential impact on the site and surrounding
area. The cumulative impact of developments will also be taken into account.
4 T h e P l a n h a s b e e n s u b j e c t t o a V i a b i l i t y A s s e s s m e n t , t o e n s u r e t h e p o l i c i e s a r e
deliverable. In the exceptional circumstances where site -specific issues generate
viability concerns, applicants should discuss these with the Council at the earliest
possible stage in the development process. Proposals that are unable to comply with
the Plan’s policies on viability grounds must be accompanied by a detailed Viability
Assessment.
5 Developer contributions in the form of the Community Infrastructure Levy will
contribute towards strategic infrastructure required to support the overall
development in the Local Plan. An element of CIL will, where appropriate, also be
utilised to delive r local infrastructure requirements in accordance with
Neighbourhood Plans, in accordance with CIL legislation.
6 Contributions secured through planning obligations may be pooled to address need or
cumulative impacts arising from more than one development proposal. The
Infrastructure Funding Statement will inform decision making on the use of planning
obligations.
7 The Council will work in partnership with infrastructure providers and other delivery
agencies in updating the Infrastructure Delivery Plan.
8 Whilst minor developments are less likely to contribute towards developer
contributions, requests may still be sought where the proposal has a specific impact
upon local infrastructure that requires mitigation in order to make it acceptable in
planning terms.
9 To support the efficient and sustainable delivery of infrastructure as part of relevant
planning applications the Council will seek a monitoring fee contribution reflective of
the sites size and capacity.
450. The paragraphs below set out the known infrastructure requirements that will need to be taken
into account within development proposals in accordance with the above policy.
Affordable Housing
451. The Council’s approach to the provision of affordable housing is set out in the chapter
“Delivering a Sufficient Supply of Homes” chapter and is referenced here just for
completeness.
Education
452. Most major residential developments result in new homes that are occupied by families with
early years or school age children, and this usually places additional demand on schools and
early years providers in the vicinity of the site. To address this dema nd the Council, as
education authority, will assess capacity at existing schools/provision and, where necessary,
will seek commuted payments to be used to increase the capacity at appropriately located
schools/provision. This will be done in a proportiona te manner taking into account the DfE's
pupil yield dashboard and revised guidance on Developer Contributions for Education (August
2023). The approach is set out in the Education Sufficiency Strategy (2025 to 2028) and the
Council’s approved Developer Contributions for Education Policy approved in January 2024.
453. The policy calculates education contributions by:
• Estimating pupil yield37 from developments using the DfE pupil yield methodology;
• Separately assessing impacts on:
• Early Years
• Primary
• Secondary
• Post-16
• SEND provision; and
• Applying a cost per place to determine the required contribution.
37 For instance, a site of 100 dwellings (40% of which would be affordable) would result in a pupil yield of 34 for
primary school and 18 for secondary schools.
454. Within the settlement chapters, more local ly specific commentary is given to education
infrastructure requirements, including where the scale and location of expected growth will
result in the need for a new school to be provided.
Education Transport
455. Whilst accessibility of new developments will be taken into account to determine whether a
particular development would be located in a sustainable location or not, there may be
occasions where dedicated school transport may be required.
456. A contribution may be sought where:
• The development is located beyond the statutory walking distance from the relevant
school and pupils generated by the development would be entitled to Council-funded
transport.
• The statutory walking distance is exceeded, namely:
• 2 miles for children under 8 years old.
• 3 miles for children aged 8 and over.
457. The contribution is based on the number of eligible pupils generated by the development × the
transport cost × the relevant number of school years.
458. Even where a development is within the statutory walking distance, if there is no safe walking
route, the Council may seek a contribution towards highway works to create a safe route to the
relevant school or a transport contribution.
Healthcare
459. The Council has been working with the Birmingham and Solihull Integrated Care Board (BSOL
ICB) to assess the healthcare infrastructure needed to support new development. This has
included the development of a model that predicts the likely additional health care
engagements/activity that would be generated by a development and converts this into the
space required to deliver the additional activity. An assessment is then undertaken to
determine whether there is any spare capacity in the area. If not, the space required to provide
the additional activity is converted into a cost that is then used to identify an appropriate and
proportionate commuted sum.
460. The model considers the impact of development on the following healthcare sectors:
• Primary Care.
• Community Care.
• Mental Health.
• Acute Outpatients.
• Acute Emergency.
461. BSOL ICB have confirmed that they will then work directly with healthcare providers (be they
GP practices and/or hospital trusts) to determine how such funds will be deployed to ensure
that appropriate capacity improvements are undertaken to the healthcare estate to facilitate
the additional demands arising from the development.
462. The Council believes that by engaging with BSOL ICB on this basis allows for a single ,
coordinated and consistent approach to be taken for developments across the Borough rather
than engaging with individual healthcare providers. This approach recognises the ICB’s role to
coordinate and plan for service delivery rather than directly providing that service.
463. It should be stressed that this approach seeks to identify the physical infrastructure needed
to support the development and does not include the operational or on -going revenue costs
of actually proving the service (for example where any additional GPs need to be provided) as
it is considered that this is more appropriately funded through general taxation that will be
generated in the area as a result of the new development/residents.
Playing Pitches & Sport Hubs
464. A s n o t e d i n a n e a r l i e r c h a p t e r , the Council’s Playing Pitch and Outdoor Sports Strategy
(December 2023) and associated Playing Pitch Assessment identifies that additional playing
pitch demand will arise as a result of new developments 38. This strategy is the current Sport
England-compliant evidence base that the Council should use when seeking playing pitch and
outdoor sports contributions through planning obligations and when assessing the impact of
Local Plan growth.
465. In assessing the quantum of additional need that may arise, the Council has used Sport
England’s Playing Pitch calculator. This is then used to calculate a proportionate and
appropriate contribution that will be used to provide additional facilities.
466. The Council is seeking to pool these contributions at a settlement level that will then be used
to bring forward sports hubs that will be larger more sustainable facilities t han had new
facilities been provided in a more dispersed and isolated fashion with smaller facilities . A
pooled approach will help ensure that contributions are sufficient to deliver strategic facilities
38 This is in addition to any replacement playing pitches may be required in connection with developments that
may take place on existing facilities, and thus the replacement pitches are required as mitigation.
capable of meeting demand generated by multiple developments and serving wider
communities. This may include associated ancillary infrastructure such as changing
accommodation, parking, access arrangements, lighting, and other supporting facilities
where appropriate.
467. Hub locations will be pursued to serve new developments at the following locations:
• Balsall Common
• Blythe
• East of Solihull.
• Knowle
468. At this stage specific sites for these hubs have not yet been identified as more work will need
to be undertaken when the actual level of growth for each location is understood through the
adoption of this plan and the determination of speculative applications that is expected to
occur before the plan is adopted. It is the level of growth that will determine the size of each
hub, and therefore the land required to support its delivery.
469. Whilst these broad locations have been identified, the precise location, scale and form of
provision may evolve as further evidence, masterplanning and development proposals come
forward.
470. Delivery of sports hubs will be pursued in partnership with Sport England, National Governing
Bodies, sports clubs, schools, community organisations, and other relevant stakeholders
where appropriate. The delivery of these hubs will play a key role in miti gating the impacts of
growth and ensuring that new and existing communities have access to sufficient, high-quality
sports and physical activity infrastructure throughout the plan period.
Public Transport
471. Whilst accessibility of new developments will be taken into account to determine whether a
particular development would be located in a sustainable location or not, there may be
occasions where public transport enha ncements are required to enable access to
developments by means other than the private car.
472. This will be assessed on a site-by-site basis and may result in the need for commuted sums to
be used toward enhancing public transport that can be used to serve the site. This could
include enhancements to bus services and/or measures to improve the accessibility of rail
services and in doing so will work with public transport providers in doing so.
Travel Plans
473. The need for travel plans is often identified through the transport assessments prepared for
major developments. Where this does illustrate the need for a travel plan the Council is open
to the developer taking on responsibility for the delivery of the plan, or if requested the Council
will do so. In these instances, this will generate the need for commuted sums to cover the
delivery costs.
Police
474. The Council will work with the West Midlands Police & Crime Commissioner to seek to identify,
where justified, infrastructure improvements that may be necessary as a result of additional
development occurring in an area. These infrastructure improvements will not be expected to
cover operational or revue related matters that are , like health services, more appropriately
funded through general taxation that will be generated in the area as a result of the new
development/residents.
475. Measures could include physical infrastructure (such as charging points for vehicles and/or
welfare facilities for officers when working remotely from a permanent base.
Other Potential Infrastructure
476. The above infrastructure needs should not be considered as a closed list , as other examples
may come forward during the plan period. Where this occurs the Council will set out a
justification for any additional payments using the principles of necessity and proportionality
that are included in the Regulation 122 tests.
Monitoring Fees
477. In addition to the above, the Council will also include a monitoring fee in relation to relevant
planning obligations. In setting the monitoring fee the Council will ensure that these will be
set based on the following considerations:
• The sum to be paid fairly and reasonably relates in scale and kind to the development;
and
• The sum to be paid to the authority does not exceed the authority’s estimate of its cost
of monitoring the development over the lifetime of the planning obligations which
relate to that development.
Recent Experience
478. Since the end of 2024 the Council has been determining a number of major residential
developments on sites (including sites within the Green Belt) and has been seeking
appropriate section 106 obligations . Th ese have included the types of infrastructure
contribution listed above. On at least one occasion, most of these contributions have also
been included in a planning permission granted on appeal 39. This is highlighted to
demonstrate that the Council’s approach to date has been in accordance with the regulations
that require such contributions to be necessary; directly related to the development; and fairly
& reasonably related in scale and kind to the development.
479. From the last quarter of 2024 until mid-2026, at least 14 major residential developments have
been granted planning permission which include proposals for up to 3,700 dwellings. The
associated S106 agreements to these applications make provision for up to £44 million in
commuted sums to be collected and used to address the infrastructure improvements noted
above. Some of these developments have not commenced, and some will have a range of
trigger points/phasing that will influence when the monies are actually paid. As payments are
made these will be reported in the Council’s annual Infrastructure Funding Statements.
Monitoring
480. The Council will develop a monitoring framework following adoption of this plan.
39 For instance, the development of 80 dwellings on land west of Stratford Road (Hockley Heath) (appeal