This section describes the UK Central Hub around junction 6 of the M42, which includes Arden Cross and the HS2 interchange site, Birmingham Airport, the NEC, Jaguar Land Rover and Birmingham Business Park. First HS2 trains are forecast between 2036 and 2039, with a journey time from London of 38 minutes. The Hub is expected to deliver many jobs and homes. Key needs include transport upgrades, a new primary school, and green and blue infrastructure. The Green Belt boundary will be amended to release Arden Cross (140 hectares) and land at Damson Parkway for employment and possible airport or JLR expansion.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
UK Central Solihull
The Area Now
771. The area known as the UK Central Hub is a significant contributor to the wider West Midlands
economy and a transport hub for the Midlands Engine. The Hub is focussed on the main
economic assets located around junction 6 of the M42. The principal elements are as follows:
• Arden Cross Land including the site of the HS2 interchange
• Birmingham Airport
• The NEC
• Jaguar Land Rover
• Birmingham Business Park
772. The Hub forms part of the wider UK Central Solihull concept which comprise s of four
interconnected economic opportunity zones. Together with the UK Central Hub which makes
up Zone 1 the UK Central also includes: Zone 2 – North Solihull, Zone 3 – Solihull Town Centre
and Zone 4 – Blythe Valley Business Park
HS2 Interchange – Arden Cross
773. The triangular shaped site that is to accommodate the HS2 Interchange station is currently a
largely open parcel of land bounded by the M42, A45 and A452.
774. Construction of HS2 has commenced in the Borough and the HS2 Interchange station will be
in the heart of the UK Central Hub on land adjacent to the NEC. It is forecast that the first trains
to run on the route will be between 2036 and 2039, at which point the journey time from
London to Interchange at the UK Central Hub will be 38 minutes.
775. The WMCA Investment Prospectus 2020 and HS2 Connectivity Package recognise the
opportunity that the HS2 rail link offers to drive economic growth and prosperity, and the
significance of UK Central, particularly the Hub Area around the Interchange station. The area
is identified as regionally significant in the WMCA Futures Green Paper (2024) and in the West
Midlands Strategic Growth Plan (2025) the UK Central Gateway is identified as a key corridor
for economic growth connecting East Birmingham to the UK Central Hub as discussed in the
economy chapter of this Plan.
776. Alongside the economic benefits the development of the hub is an opportunity as part of the
wider UK Central proposals to improve links with the surrounding area in particular North
Solihull with the prospect for improved access to employment.
Birmingham Airport
777. Birmingham Airport is the principal international gateway into the Region and has a major role
in the national airport infrastructure. It is a key economic growth driver, particularly regarding
the knowledge economy, high value-added sectors and overseas inward investment and
international trade. The development of new long-haul routes enabled by the main runway
extension, completed in 2014, enhance the Airport’s capacity to contribute to local and
regional economic growth as a key component of UKC. The HS2 Station will improve the
accessibility and attractiveness of the Airport from further afield, particularly London and the
South-East.
National Exhibition Centre (NEC)
778. The continued success of the NEC is important to the local and regional economy and is the
UK’s largest exhibition centre. The role of the NEC has evolved from its early exhibition centre
beginnings in the 1970’s to become a major events, tourism and leisure venue, serving both
business and leisure markets and contributing significantly to Solihull’s and the Region’s
visitor economy. The opening of Resorts World (a £150 million mixed use leisure development)
in 2015 demonstrated the evolving role that the NEC plays.
779. The NEC have set out evolving proposals for future employment-led economic growth at the
site. The Local Plan provide s a framework to allow the NEC to take advantage of future
opportunities and continue to evolve.
Jaguar Land Rover (JLR)
780. Jaguar Land Rover is one of the West Midlands’ , and UK’s, most important businesses, as an
advanced manufacturing firm developing leading technologies including in low emissions
vehicles.
781. Part of the area beyond the northeast of the existing plant has been developed to provide a
14ha vehicle despatch area which opened in 2015. The Council considered that there were
very special circumstances for allowing this development in the Green Belt. This was to
support the operational needs of this internationally significant company that needs to remain
competitive in the global vehicles market in order to continue to support significant numbers
of jobs in the Region that rely on the success of JLR. In 2021 a large scale (over 90,000 sqm)
development for J LR was opened. It is a major logistics and warehousing facility used to
support vehicle production.
Birmingham and Blythe Valley Business Parks
782. Birmingham and Blythe Valley Business Parks have successfully attracted new investment to
Solihull and the Region in accordance with their original role of helping to modernise and
diversify the Region’s economy by attracting knowledge-based employment and combatting
decline in the Region’s manufacturing base. Birmingham Business Park is well placed near
Birmingham Airport and the NEC to encourage new growth and investment. Blythe Valley
Business Park is competitive with the south-east and M40 corridor and is capable of
developing new facilities to promote and support innovation and entrepreneurism.
783. These two high quality, managed business parks have a key role in Solihull’s success in
attracting business investment in high value-added sectors including ICT, business and
professional services, creative industries, construction and engineering. It is important that
these high-quality sites continue to attract knowledge economy investment to Solihull and the
Region, thereby underpinning economic recovery and growth. This includes further realising
the potential of Blythe Valley Business Park as a location for innovation uses and new
enterprise. There is also potential for Birmingham Business Park to play a greater role in linking
investment and employment opportunities to the North Solihull area.
To reinvigorate these sites, the range of acceptable uses on them was broadened under the
2013 Solihull Local Plan in response to changed market conditions. There is growing
competition from town and city centre locations as occupiers realise the benefits to
employees of access to a range of facilities and to public transport. Better facilities will be
needed if they are to continue to secure appropriate investment.
The Area in the Future
784. It is anticipated that the UK Central Hub Area will make a significant contribution towards the
delivery of homes and economic development in the Borough during the plan period and
beyond. The extension of high-speed rail to the West Midlands will be significant, reducing
journey times to London to 38 minutes and enhancing existing connectivity provided via
Birmingham Airport and via the region’s extensive road and motorway network. As the site of
the first high speed station outside London, the Hub Area is uniquely placed to capture these
benefits.
785. T h e H u b A r e a i s t h e r e f o r e a u n i q u e s i t e w i t h t h e p o t e n t i a l t o d e l i v e r m a j o r g r o w t h o n a
nationally significant scale both to meet the economic growth aims of the Borough as well as
the wider growth aspirations of the West Midlands Combined Authority.
786. It is clear that co -ordinating the development ambitions of all stakeholders and delivering a
range of growth opportunities will provide multiple benefits for the Borough and wider area
including:
• The delivery of a significant amount of jobs
• A greater range and choice of new homes for The Hub, Solihull and the wider Housing
Market Area
• New and unique forms of high-quality development
• The creation of healthy neighbourhoods
• Joined up green infrastructure
• The delivery of strategic infrastructure
What is required for the settlement in the future
787. Coordinated approach - The delivery of the Hub area is complex and a coordinated approach
by all stakeholders is necessary. The Council have therefore been working closely with all key
stakeholders including: Birmingham City Council, the West Midlands Combined Authority
(WMCA), Arden Cross Limited, the NEC, Birmingham Airport, Jaguar Land Rover, Birmingham
Business Park, Highways England, relevant utilities companies and HS2 Ltd.
788. A UK Central Hub Growth and Infrastructure Plan (January 2018) and Framework Plan
(February 2018) was prepared to align the growth aspirations of all these key stakeholders and
provide an overall view of how development and infrastructure can be delivered across the
Local Plan period. A primary focus of this is to ensure that constraints to development such as
crucial infrastructure requirements are addressed in the early stages to ensure the high
economic growth aspirations of the site can be delivered.
789. In terms of delivering the vision and objectives for the site and address the key challenges the
Hub framework is based on five key place making principles. These have been designed to
guide a common approach to development across the site:
• Improve accessibility
• Establish a high quality green and blue network
• Create sustainable, high-quality communities
• Leverage land with temporary uses
• Generate a clear sense of place
790. Development Principles - It is important that there is an overall place making vision for the
Hub based on a clear set of development principles to support the creation of a
sustainable high-quality environment and to ensure the necessary infrastructure is in place to
deliver and support growth aspirations for the site.
791. The Arden Cross Masterplan (2020) set out a comprehensive set of principles for delivering the
vision and development of the Arden Cross site. These will be key in supporting the
development of the Hub Area. Muse Ltd have been appointed as the development partner for
Arden Cross and are undertaking further work to develop the vision and masterplan for the
site.
792. Transport Infrastructure - A significant amount of transport infrastructure will
be required to assist in the delivery of the site. Primary road infrastructure upgrades are
already being pursued including changes to Junction 4 of the M6, Junction 6 and the opening
of a n e w J u n c t i o n 5 A o f t h e M 4 2, providing links to the site in preparation for the
implementation of HS2. As an example of collaborate planning and delivery, the Roundabout-
over-the-Trace, which provides the main access into Arden Cross and the HS2 Interchange
Station, has already been designed and constructed to accommodate development at Arden
Cross beyond what would be required to service HS2 only. Led by the Council, in partnership
with HS2 and DfT, West Midlands Combined Authority funded the creation of this critical
additional capacity.
793. HS2 will be providing an Automated People Mover (APM) connecting the interchange station
with the NEC, Birmingham International Station and Birmingham Airport. A Metro tram route
is proposed from Birmingham City Centre through East Birmingham and North Solihull to the
UK Central Hub.
794. Social and community infrastructure – It is important that the full range of facilities
necessary to support the creation of a high-quality sustainable community at The Hub are
provided. These include healthcare and education facilities to serve residents of The Hub but
also the potential to capture the wider benefits of the scheme by enhancements to
infrastructure serving the wider community . This also includes improving access to jobs and
working towards improving the skills base. During the plan period it is expected that a new
primary school will be required to serve the new community. It is recognised that growth will
continue beyond th e plan period and additional social and community infrastructure will be
needed, which could include a new secondary school depending on the scale (and
composition) of residential development in the long term.
795. Green and blue infrastructure – It is proposed that a network of green and blue infrastructure
will be integrated throughout the development with the intention to provide a high-
quality sense of place . The provision of Green Infrastructure is a particularly important
element as it will allow existing features to not only be retained but enhanced as part of an
integrated approach.
Proposed approach
796. The Green Belt boundary will need to be amended to accommodate the land at Arden Cross
(140 hectares) and in order to deliver wider development at The Hub. This will facilitate the
delivery of the site alongside development at the NEC which is already outside the Green Belt.
797. The UK Central Hub proposals are site specific as they are dependent on the delivery of HS2
and the Interchange station and will assist in delivering the needs of key economic assets
supporting the local and regional economy. The land is bounded by main roads that provide
strong defensible Green Belt boundaries. The exceptional circumstances set out in Policy
SMBC/UK1 for releasing the Arden Cross Land from the Green Belt are therefore justified.
798. The delivery of The Hub site is complex, and the Local Plan may also need to take forward other
relevant elements of the wider proposals being developed by key stakeholders to realise
development. Land at Damson Parkway will also need to be released from the Green Belt in
order to allow development to meet local and strategic employment need and potential
ancillary development to meet the future expansion of Birmingham Airport or JLR.
799. It is anticipated that HS2 will be operational between Birmingham and London between 2036
to 2039. It is expected that land around the HS2 interchange station will be available from 2030
therefore detailed planning and delivery preparation can be undertaken ahead of this on the
first phase of the development. Given the timescales it will be necessary for the Local Plan
to retain a degree of flexibility in dealing with the site to take account of the emerging plans.
800. The site will have wide implications in terms of economic growth serving a large geographical
area across the Borough’s administrative boundaries. The Council will continue to engage with
neighbouring authorities as well as other local authorities across the region as the proposals
go forward to understand the impact. Given the nature of the proposal, it is important that this
is maintained as a fluid process and reflects the importance of ongoing engagement and
collaborative working as part of the Duty to Cooperate. The Council is engaging with WMCA
and neighbouring authorities on the preparation of the SDS.
801. In bringing forward development at The Hub regard will also be given to proposals affecting the
wider site noted in the following paragraphs.
802. National Exhibition Centre (NEC) – Work undertaken by the NEC since the previous Local
Plan Review examination has identified potential for employment led development including
an Industrial and Logistics Hub utilising car parking and underused land to the North of the
site. This is a shift away from the position in the 2020 plan that was seeking a residential led
masterplan60. The Local Plan will need to be flexible to respond to future growth aspirations of
the NEC.
803. Jaguar Land Rover expansion – Land at Damson Parkway is being removed from the Green
Belt to accommodate employment development (see Policy SMBC/UK2). This also r eflects
the historic position whereby development to support the operational requirements of JLR
have already taken place in the Green Belt through developments (for example the despatch
area and Logistics Operation Centre) that were approved under very special circumstances. If
further additional space is required, then this would be an appropriate use under Policy
SMBC/UK2.
804. Birmingham Business Park – The Park already occupies an important role as a prime
employment location. It is important that the wider proposal for The Hub builds upon this.
805. Birmingham Airport Masterplan (2018) – The masterplan (published pre-Covid 19) for the
airport predicts growth in passenger numbers per year from 13 million in 2018 to 18 million
in 2033 and considers the potential for and implications of higher growth levels to 24 million.
It is framed in the context of the national policy to mak e best use of the existing extended
runway. It sets out plans for £500 million of new investment to expand the terminal building,
increase the number of aircraft stands, extend ancillary facilities and interconnect with HS2.
It highlights a need for more land for ancillary facilities beyond the existing Airport area
and identifies land near Elmdon and JLR, which includes land allocated for employment
development at Damson Parkway. This is in the context of maximising the benefits of HS2 and
the wider proposals for UK Central Solihull. The allocation of UK2 allows flexibility to respond
to these potential needs in the future.
806. Work is being undertaken by the Airport to publish an updated Masterplan, this is expected to
be published in 2026.