This section sets out the education allocations. A new secondary school site is allocated at Carpenders Park Farm, Oxhey Lane (ED1), able to accommodate a school of up to 10 forms of entry serving Carpenders Park, South Oxhey, Eastbury and parts of neighbouring boroughs. Land including and adjoining The Reach Free School (ED2) is allocated for a new secondary school or a four form entry expansion, and a primary school site at Woodside Road, Abbots Langley (ED3) is carried over from 2014. Identified school sites will be safeguarded for educational use.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
8 Education
8.1 It is vital that necessary infrastructure and services, including education, are
integrated into new developments. Proposals must address such requirements for
new and improvements to infrastructure directly through on-site provision or through
the Community Infrastructure Levy which applies to certain forms of new
development.
8.2 Where education provision is required on -site, this may be in the form of a new
education facility or the expansion of an existing facility. Site -specific comments on
the housing site allocation policies identify where housing sites would be required to
contribute to meeting education needs through the provision of a new facility or the
expansion of an existing facility.
8.3 In addition to the housing sites which would be required to provide education facilities,
there is a site which has been allocated for a secondary school located to the
northeast of Carpenders Park (ED1). Hertfordshire County Council is responsible for
the provision of schools in the district and has identified a need for a secondary school
facility in this location in order to serve the future secondary education needs of the
education catchment area (including Carpenders Park, South Oxhey and Eastbury in
Three Rivers as well as areas in the Hertsmere and Watfor d Boroughs).The district
has education facilities with capacity for either extensions to existing schools or the
building of new schools. The remainder of land, for example at Long Lane, has been
retained as an education allocation in the Plan to facilitate a new secondary school
(or expansion of the Reach Free School) to meet additional demand arising from new
development in the west of the district. This has been given the site reference ED2.
8.4 The pre-existing Site Allocations LDD (adopted 2014) allocated a site reference S(c)
(Woodside Road, Abbots Langley), for primary education, however, this has not yet
commenced. As such, this allocation has been retained within this Local Plan and
given the site reference ED3.
8.5 The Education Allocations policy and education site allocation policies can be seen
below.
Education Allocations
1) Three Rivers District Council will continue to work with the County
Council, adjoining authorities and other interested parties to identify the
most appropriate sites to meet identified educational needs.
2) Identified education sites for new primary or secondary schools will be
safeguarded for educational use.
Site
Ref
ED1 Site Carpenders Park Farm, Oxhey
Lane
Size (ha): 8.2
Current
Use Agricultural
Proposed
Use
Secondary
education
Green Belt The site is in the
Green Belt
Phasing 1-10 years
Comments
The site is suitable to accommodate up to a 10 form entry secondary school. A detailed heritage
impact assessment and an archaeological assessment would be required prior to any
development in order to protect and mitigate any potential adverse impacts to heritage assets.
Development would need to satisfactorily address surface water flood risk on the site by
providing suitable mitigation. Measures to avoid adverse impacts and enhance biodiversi ty
would need to be provided due to the location of a Local Wildlife Site which is adjacent to the
site. Maps provided by Cadent Gas shows Low/Medium pressure gas pipes in the vicinity of
the site (west of the site along edge of Oxhey Lane) and it is likely that there are gas services
and associated apparatus in the vicinity so their presence should be anticipated. This does not
prevent development of the site but will require an appropriate buffer from the pipeline to
development and is an issue to be addressed at the planning application stage.
Site
Ref
ED2 Site Land including and adjoining The
Reach Free School
Size (ha): 19.3ha
Current
Use
Secondary School
& associated land
and agricultural
land
Proposed
Use
Secondary
education
Green Belt
The southern
section of the site
is not located
within the Green
Belt. The
remainder of the
site is in the
Green Belt.
Phasing 1-10 years
Comments
To the southwest of the site is the Reach Free Secondary School. The school and ancillary
uses including playing fields and car park form an approximate “L” shape from the western
boundary to the southeastern boundary of the site . The remainder of the site is currently
agricultural land. The entire parcel of land within the red line boundary is being allocated to
safeguard future secondary education use either via the expansion of The Reach Free School
(additional 4FE) or the construction of a new secondary school.
Site
Ref.
ED3 Site Woodside Road, Abbots Langley Size (ha): 2.5ha
Current
Use Agricultural
Proposed
Use Primary education
Green Belt The site is in the
Green Belt.
Phasing 1-10 years
Comments
The site is a pre-existing education allocation from the Site Allocations LDD (adopted 2014).
The site is allocated for primary edu