This section introduces the Daventry chapter. Daventry grew from about 4,000 people in 1950 to around 28,000 in 2021 after being used for overspill development from Birmingham. The chapter describes regeneration schemes such as the Abbey Retail Park, the iCon building and the Arc cinema, and green features such as the Country Park and Borough Hill. It covers housing, including 450 homes under construction at Micklewell Park and 4,000 homes allocated at Daventry North East. A 2022 study found town centre vacancy of 13.1%, below the national average of 14.1%. The strategy supports continued growth.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
Chapter 6: Making Great Places - Daventry
6.1. Introduction
6.1.1. Daventry was a small market town until the 1960s when it was identified as a
location for overspill development from Birmingham. As a consequence, the
population of Daventry has grown over the years from about 4,000 in 1950 to
around 28,000 in 2021.
6.1.2. In the early 2000s, the former Daventry District Council supported the further
growth of the town in order to support the town centre, which was in need of
some revitalisation and regeneration. Various options studies and masterplans
were commissioned by the Council to assist in the development of planning policy.
6.1.3. The WNJCS supports the regeneration of the town including through significant
new retail floorspace in the town centre and through the allocation of land for a
sustainable urban extension to the north east for about 4,000 houses. At the time
the plan was adopted, it was expected that 2,600 of these would be built in the
plan period (up to 2029).
6.2. Daventry today
6.2.1. Various schemes to regenerate Daventry have been implemented, including the
Abbey Retail Park, the ‘iCon’ building and more recently the ‘Arc’ cinema
development. However, some of the more ambitious schemes such as the
significant additional retail floorspace which was initially planned for the north of
the High Street and subsequently off Ashby Road have not come to fruition.
6.2.2. The town retains its historic core, which comprises several shopping streets with a
high number of listed buildings, surrounded by areas of high density and terraced
housing. It benefits from a recently reviewed conservation area designation and
related Article 4 directions in the central area. Daventry has local green links
comprising wide landscaped verges which are a particular feature related to its
history as a planned expanded town. The Country Park, centred on Daventry
Reservoir with links to the canal network, is a key component of the green
infrastructure network which connects the town to the wider countryside. Borough
Hill, which wraps around the south eastern edge of the town, is a significant
historic landscape feature and scheduled monument.
6.2.3. The Daventry Development Link Road, which provides a route from Daventry
to Northampton and the M1, bypassing Flore and Weedon was opened in
2019.
Homes
6.2.4. From the start of the WNJCS plan period (2011) to 2025 the number of homes
built per year has averaged 150 (2257 in total) within a range of 2 to 306.
6.2.5. At Micklewell Park a scheme is under construction for 450 homes. An
extension to this development was allocated in the Settlements and
Countryside Local Plan (S&CLP) for 250 homes and planning applications are
expected on the extension in 2026. An additional area to the north of the
existing extension is proposed in this Plan for 180 homes, giving a total of
approximately 430 homes.
6.2.6. Development is also underway on a site to the south west of Daventry
allocated in the S&CLP. This site was allocated for 1,100 homes, but
permission has been granted in full for 140 dwellings on part and in outline
for up to 1,100 on the remaining part. Both schemes are under construction.
Reserved Matters Approval has been granted for 418 dwellings on the part
with outline for 1,100. Given the progress made on this site it is anticipated it
will be built out completely in the plan period.
6.2.7. Land to the north east of Daventry is allocated for 4,000 dwellings in the
WNJCS. An outline planning application is expected to be determined shortly.
However, because the planning application has not been determined, it is re-
allocated in this Plan.
Employment and economic growth
6.2.8. Employment floorspace in the town is concentrated in a small number of large
industrial/commercial estates located to the north west and south east of the
town. Daventry International Rail Freight terminal located some six miles to
the north continues to grow and provides employment opportunities for
residents of the town. The S&CLP identified the need to provide employment
land to accommodate small scale businesses in the town, and accordingly a
number of allocations were made to facilitate this.
6.2.9. Of those allocations: Land to the North West of Nasmyth Road has planning
permission and is substantially under construction; Land off Newnham Drive
has been partly completed and part has planning permission, a small part
remains undeveloped and is re-allocated in this Plan; The Knoll has been
developed.
Town Centre
6.2.10. A study of the town centre in 2022 concluded that the centre has a relatively
good balance of independents and multiples and that the retail offer is
anchored by its three main foodstores. It had a vacancy level of 13.1%, below
the national average of 14.1%. The report also observed that the centre has
benefitted from significant new investment over recent years including the
new 4-screen cinema.
6.3. Strategy for Daventry
6.3.1 The strategy for Daventry is to support continued growth, recognising its role in
the settlement hierarchy.