This section introduces the new Solihull Local Plan. It notes that two thirds of the Borough is in the Green Belt, including the Meriden Gap that separates Solihull and the Birmingham conurbation from Coventry. The current plan was adopted in December 2013 and covers 2011 to 2028, but is now seen as largely out of date. A 2020 Draft Submission Plan was withdrawn in October 2024 after a long examination. This plan replaces the 2013 plan and the 2014 Gypsy and Traveller Site Allocations DPD. Without a plan, the Council could not show a 5-year land supply. Five neighbourhood plans have been made and remain part of the development plan.
An unofficial plain English summary. The official wording below is
what counts at examination; check it before you rely on anything here.
What the plan says
The text below is extracted automatically from the official PDF and may
contain artefacts; the PDF is authoritative.
Introduction
Importance of a Plan Led System
1. At the heart of planning is the need to plan positively for sustainable development. One of the
principal ways this is achieved is by having a local plan to guide the development of an area.
Solihull Council’s local plan is key to delivering sustainable, infrastructure led development
that reflects the vision and aspirations of local communities. The aim is that local authorities
should positively seek opportunities, through their local plan, to meet the development needs
of their area. The Council’s local plan addresses the spatial implications of economic, social
and environmental change that is happening to the Boro ugh, both now and in the future. It
promotes an infrastructure led strategy to meet the development needs of the Borough,
delivering homes and employment opportunities for local communities.
2. Two thirds of the Borough is located in the Green Belt, and this includes the strategically
important Meriden Gap that separates Solihull and the Birmingham conurbation from the city
of Coventry. This plan seeks to protect this important feature that makes Solihull special
whilst accommodating, in a managed way, the growth that is needed.
3. The current local plan, the “Solihull Local Plan” (SLP), was adopted in December 2013 and
covers the period 2011 to 2028. Whilst the content of the Plan remains broadly consistent with
key aspects of national policy, the evolution of the National Planning Policy Framework (NPPF),
especially in recent years and the increase in the nationally derived housing requirement mean
the plan is now considered largely ‘out of date' .
4. In October 2020 the Council published the “Solihull Local Plan – Draft Submission Plan”1 . It
was subsequently submitted for independent examination in May 2021. During the course of
the examination significant changes and intended changes to national planning policy were
made and this impacted on the examination process such that the Inspectors eventually
recommended that the plan be withdrawn, which then took place in October 2024.
5. This plan has therefore been produced as a replacement to the 2013 plan as the 2020 wasn’t
able to be pursued to adoption.
Glossary of Terms
6. Planning can be quite a technical and complex area and often uses unfamiliar terms. Whilst
this document has been written as plainly as possible, it has had to use some technical terms
and many abbreviations. To help understand the document a glossary and schedule of
abbreviations has been provided towards the end of this document.
How Could it Affect Me?
7. The local plan as a whole sets out the future spatial strategy for the Borough. It is key to
delivering sustainable, infrastructure led development that reflects the vision and aspirations
of local communities and includes the allocation of sites to promote development. It also
identifies land where development would be inappropriate because of its impact on, for
instance, environmental or historic assets; and it also incorporates a strategy for enhancing
the natural, built and historic environment.
What will happen if we don’t identify enough land for new
development?
8. National planning policy is that the supply of land for housing should be significantly boosted,
and without an adequate supply of land for new dwellings, access to the homes that we all
need becomes ever more difficult. Equally, land for commercial needs has to be managed to
ensure that existing businesses can flourish whilst also providing an opportunity to attract
new business into the Borough. Of course, we also need to recognise the special place that
Solihull is, and this plan seeks to ensure that the right balance is achieved between providing
land for new development and protecting what makes Solihull special.
9. If the Council does not have an appropriate plan in place, it will be unable to demonstrate a ‘5-
year land supply’ . This is already a pressing issue in the Borough following changes to the
national housing requirement in December 2024 and means policies in the 2013 plan would
be considered out -of-date and lead to less influence over the impact, including through
inappropriate design, that some developments may have. This increases the Borough’s
vulnerability to speculative development proposals and would lead to development and
growth taking place in an unplanned manner, placing additional pressure on infrastructure
without guaranteeing or planning positively for measures that can mitigate the impacts. In
addition, the Secretary of State could inte rvene in the Council’s plan making powers thus
taking away local choice about where development should be accommodated.
1 A plan prepared under Regulation 19 of the plan making regulations.
Background
10. This plan has been developed in a way that represents an evolution of the Local Plan Review
that was withdrawn from examination in October 2024. This included significant consultation
which helped to shape the plan and its contents.
11. The previous Local Plan Review was subject to a series of stages which started with a scope,
issues and options consultation in November 2015; and further consultations on draft
versions of a plan in November 2016 and January 2019. These earlier stages, and the evidence
base prepared to support this plan culminated in the Draft Submission Plan being published
for consultation in October 2020. It was subsequently submitted for examination in May 2021.
The Plan was subject to a protracted examination period, caused in part by changes to national
policy and a small number of key issues regarding housing land supply. The Inspectors
overseeing the examination recommended the Plan be withdrawn in September 2024, which
was confirmed through a meeting of the Full Council the following month.
12. Despite its withdrawal much was achieved through the examination of the draft Plan,
including:
• The inspector confirmed the duty to cooperate had been complied with;
• The Spatial Strategy was deemed acceptable in principle;
• The housing requirement, including its basis as a stepped requirement, was agreed in
principle; and
• The proposed residential site allocations were confirmed as acceptable in principle.
13. A key step in withdrawing the previous Plan Review was the approval of a Position Statement
to help form the basis for the next Plan ’s development. This recognised the opportunity for a
new Plan to represent an evolution of the previous Plan Review as opposed to a fundamentally
different strategy.
14. Further changes to national policy and legislation since July 2024 meant the council undertook
work to determine the best way to produce a new plan and whether that would be best served
under the new plan-making system
2 or the l egacy approach3. This work resulted in a letter
being received from the Minister for Housing and Planning in December 2025 encouraging the
Council to produce a plan under the legacy system.
15. The Council subsequently undertook a consultation4 in January 2026 on issues and options
for the new plan. The feedback to that consultation has helped shape this new draft Local
Plan.
2 The new plan-making system covers plans that will be prepared and amended under the Planning and
Compulsory Purchase Act 2004, as modified by the Levelling-Up and Regeneration Act 2023.
3 The legacy plan-making arrangements cover plans that will be prepared and amended under the Planning and
Compulsory Purchase Act 2004 which should be submitted for examination by 31st December 2026.
4 This was under regulation 18 of the (legacy) plan-making regulations.
Relationship to Other Plans
16. This plan replaces both the Solihull Local Plan (2013) and Gypsy and Traveller Site Allocations
Development Plan Document (DPD) (2014) which will no longer form part of the development
plan for the Borough once this plan is adopted.
Neighbourhood Plans
17. There are now five neighbourhood development plans that have been “made”5 . Whilst they
were prepared under the provisions of the 2013 Local Plan, they will remain part of the
development plan for the Borough where there is no conflict with the strategic policies of this
plan. In addition to the five Neighbourhood Plans a further five areas have signalled an
intention to produce a Neighbourhood Plan. Others that come forward, or updates to existing,
will need to reflect the strategic policies of this plan.
18. The Council places great importance on Neighbourhood Plans and recognises the substantial
efforts that communities have made in bringing forward plans. In the context that this plan
provides a number of policies that include Borough wide standards or expectations, there may
be occasions when existing neighbourhood plans (particularly if they are up to date and reflect
current evidence) provide a more appropriate local expression of a standard or expectation
that should be taken into account and given due weight.
19. The local authority will continue to work with neighbourhood groups, parish councils and
Neighbourhood Forum(s) to support the ongoing delivery of new neighbourhood plans and the
update of existing plans as appropriate and in accordance with national guidance.
20. The ‘made’ neighbourhood plans in the Borough are as follows:
• Hampton in Arden – August 2017
• Knowle, Dorridge & Bentley Heath – April 2019
• Berkswell – September 2019
• Balsall – June 2021
• Meriden – June 2021
5 ‘Made’ is the term given to NDPs that have been adopted.